Differences between revisions 210 and 293 (spanning 83 versions)
Revision 210 as of 2017-12-15 09:18:41
Size: 7152
Comment:
Revision 293 as of 2018-02-09 09:09:28
Size: 7878
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
2017/2/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
Line 20: Line 19:
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑

 * BS PDセット
  * 12/15 横澤
 * Beam leading to REFP port
  * *Izumi
Line 62: Line 54:
2017/12/15(Fri.) 2017/2/9(Fri.)
Line 64: Line 56:
 * Daily
  * 報告と作業 (*:責任者)
 * Remote participants by eZuce: None
Line 67: Line 58:
   * アラインメント: *和泉、長野、川崎、榎本
    * BSのアルミ箔を外し、EYのPDに光をあてる。
    * IMMT2のピコモーターがスタックしているようなのでそれを直す。
    * EYのPDを回収して、スリットを使いEYのアラインメントをする。
     * Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。
    * BSで光が見えたらゴール。
 * Report of work (*:responsible person)
  * Alignment and Vibration Isolation: *Miyakawa
   * Drift by cooling is small.
Line 74: Line 62:
   * Type B(BS): *正田、和泉、長野
    * TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。
  * Cooling: *Kimura, Suzuki, Yokozawa, Aso, Miyakawa, Miyamoto
   * One of the cooled was stopped due to the leak of water. This will be fixed in the next week. It does not affect the schedule of cooling. (Kimura)
   * PLC values are fixed. Power cable on the wall once accidentally might be unplugged and plugged, then PC was not turned on. (Aso)
   * Some of the temperature channels have been fixed. (Miyakawa, Miyamoto, Yokozawa)
Line 77: Line 67:
   * Type A(ETMY): *牛場、宮本
    * 揺れはOplevでみて数uradになっている。
    * アラインメントはなんとか出るところまでは持っていけた。
 * Work plan (*:responsible person)
Line 81: Line 69:
   * PD設置: *横澤
    * 和泉君の指示で移動のタイミングを横澤君に知らせる。

   * BSカメラ設置: *苔山、長野
    * 午後様子を見て問題がなければBS内が見えるようなカメラを設置する。外からの作業なので、他の作業と並行して作業可能。

  * Laser hazard
   * センターは変わらずSR奥。
   * 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。
 * Laser hazard: PSL room in the morning. IMM in the afternoon.
Line 92: Line 72:

  * 12/11の週
   * ETMYからの戻り光確認。

  * 12/18の週
   * EYC閉止
  * Week of 2/5
    * 2/7 Cooling.
Line 100: Line 76:
 * Issues
Line 101: Line 78:
 * 問題点など
Line 113: Line 89:
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
Line 120: Line 102:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 127: Line 109:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/5 updated KAGRA/Commissioning/Commissioning_schedule_20180206.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/9(Fri.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and Vibration Isolation: *Miyakawa
      • Drift by cooling is small.
    • Cooling: *Kimura, Suzuki, Yokozawa, Aso, Miyakawa, Miyamoto
      • One of the cooled was stopped due to the leak of water. This will be fixed in the next week. It does not affect the schedule of cooling. (Kimura)
      • PLC values are fixed. Power cable on the wall once accidentally might be unplugged and plugged, then PC was not turned on. (Aso)
      • Some of the temperature channels have been fixed. (Miyakawa, Miyamoto, Yokozawa)
  • Work plan (*:responsible person)
  • Laser hazard: PSL room in the morning. IMM in the afternoon.
  • Weekly
    • Week of 2/5
      • 2/7 Cooling.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)