Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/2/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
Line 20: Line 19:
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑

 * BS PDセット
  * 12/15 横澤
 * Beam leading to REFP port
  * *Izumi
Line 62: Line 54:
2017/12/20(Wed.) 2017/2/7(Wed.)
Line 64: Line 56:
 * 作業報告 (*:責任者)
  * Alignment of ETMY: *和泉、牛場、佐藤、都丸、高橋
   * BSからETMYはpitchに10uradくらいのズレがあったが、Oplevを見て戻すと特に問題なく光はエンドに当たった。
   * スリットを使う(三代木法)ことで、BS側に戻すのも相当順調だった。実際にスリットを外してすぐにBSのPDが反応した。
   * ETMYのPayloadのYawに200uradくらいの揺れが残っている。ヒートリンクに触ってしまった可能性が高い。ダンピングが必要。
    * Pitchも数十urad位揺れている。Pitchはおそらく上からのエアーで揺れている可能性が高い。
   * 光はYendで14000カウントでていたが、BSで6000カウントになった。予測とほぼ一致している。
 * Remote participants by eZuce: None
Line 72: Line 58:
  * IMMTが動かない件
   * IMMT2のYawのピコモーターが一方向には動くが、逆方向には動きにくい。手でネジを回すと一旦直る。すでに2-3度起きているので、再現性がありそう。
   * DACカードの順序が入れ替わっているようである。->DGS
 * Report of work (*:responsible person)
  * Alignment and Vibration Isolation: Izumi, Okutomi
   * Searching optimal position of IP of ETMY resulted that the stiffness (DC response level) is the same as what it was measured in the air. Still something at lower stage might be hitting somewhere.
  * Mirror view by Tcam also moved by 6mm order! It means that the calibration of LVDT can be wrong by factor of 25.
  * The result of fine tuning showed 1mm off to -x direction.
Line 76: Line 64:
  * IOO: 苔山、古畑、坂本、北澤
   * ISSのアラインメントがほぼ完了。AOMを触らなければならない時点でストップした。
   * MCのBURTがきちんと戻っていなかって、MCのサーボのゲインが間違っていたのでMCが不安定だった。直したら、安定になった。(和泉)
 * Vacuum: Kimura
  * Another leakage was found with 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling.
Line 80: Line 67:
 * 作業予定 (*:責任者)
  * Alignment of ETMY: *和泉、高橋、牛場、都丸、宮本
   * Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。
 * Work plan (*:responsible person)
Line 84: Line 69:
  * IOO
   * アラインメントがあるので、今日の作業は他のことをする。
  * Cooling: Kimura, Suzuki, Yokozawa
   * We will start cooling around 11AM.
Line 87: Line 72:
  * BS: Oplevの位置の初期化をしたい。   * Alignment: Izumi, Miyakawa
   * Oplev of ETMY will be monitored at the control room, and misalignment will be restored remotely during the cooling.
Line 89: Line 75:
 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。
  * WAB cooling test: Akutsu
   * Temperature monitors are being prepared.
   * Oplev is ready.

 * Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area.
Line 94: Line 82:

  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。

 * Week of 12/25
  * 停電の可能性あり。
  * Week of 2/5
    * 2/7 Cooling.
Line 104: Line 86:
 * 問題点など
 * Issues
  * IP drifted 2mm in the air, and another 2mm when pump down.
Line 117: Line 99:
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 125: Line 112:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 132: Line 119:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/5 updated KAGRA/Commissioning/Commissioning_schedule_20180206.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/7(Wed.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and Vibration Isolation: Izumi, Okutomi
      • Searching optimal position of IP of ETMY resulted that the stiffness (DC response level) is the same as what it was measured in the air. Still something at lower stage might be hitting somewhere.
    • Mirror view by Tcam also moved by 6mm order! It means that the calibration of LVDT can be wrong by factor of 25.
    • The result of fine tuning showed 1mm off to -x direction.
  • Vacuum: Kimura
    • Another leakage was found with 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling.
  • Work plan (*:responsible person)
    • Cooling: Kimura, Suzuki, Yokozawa
      • We will start cooling around 11AM.
    • Alignment: Izumi, Miyakawa
      • Oplev of ETMY will be monitored at the control room, and misalignment will be restored remotely during the cooling.
    • WAB cooling test: Akutsu
      • Temperature monitors are being prepared.
      • Oplev is ready.
  • Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area.
  • Weekly
    • Week of 2/5
      • 2/7 Cooling.
  • Issues
    • IP drifted 2mm in the air, and another 2mm when pump down.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members