2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/1/30 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 * BS PDセット * 12/15 横澤 |
* Beam leading to REFP port * *Izumi |
Line 62: | Line 54: |
2017/12/21(Thu.) | 2017/1/30(Tue.) |
Line 64: | Line 56: |
* Report of work (*:責任者) * Alignment of ETMY: *Ushiba, Sato, Takahashi R, Miyamoto, Tomaru, Yokozawa * Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。 |
* Remote participants by eZuce: Miyoki |
Line 68: | Line 58: |
* BS: Oplevの位置の初期化をしたい。 | * Report of work (*:responsible person) |
Line 70: | Line 60: |
* Work plan (*:責任者) | * Alignment * 数時間単位の線形レンジを振り切るような数100uradの大きな振動がある。Excitationが以前収まらない。 |
Line 72: | Line 63: |
* WAB: 目視でダンプの確認。 | |
Line 73: | Line 65: |
* Laser hazard * センターはSR奥がハザードエリア。 * 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。 |
* Work plan (*:responsible person) * Vacuum: leak check * WAB: Opleveのチェック * Laser hazard: PSL area |
Line 79: | Line 73: |
* Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. * 1/30-2/2 Re-checking main beam to ETMY |
Line 84: | Line 78: |
* Week of 12/25 * Planed power outage in the afternoon on 12/15. |
* Week of 2/5 * 2/5 Cooling start. |
Line 89: | Line 83: |
* k1imcでDACの入れ替えが起こっている | * Network cableの整理 * ETMYのピコモーターの反応がなくなる。 |
Line 101: | Line 96: |
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 109: | Line 108: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 116: | Line 115: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/30 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/30(Tue.)
- Remote participants by eZuce: Miyoki
- Report of work (*:responsible person)
- Alignment
- 数時間単位の線形レンジを振り切るような数100uradの大きな振動がある。Excitationが以前収まらない。
- WAB: 目視でダンプの確認。
- Alignment
- Work plan (*:responsible person)
- Vacuum: leak check
- WAB: Opleveのチェック
- Laser hazard: PSL area
- Weekly
- Week of 1/29
- 1/29,30 leak check.
- 1/30 Opening ETMY gate valve.
- 1/30-2/2 Re-checking main beam to ETMY
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/29
- Issues
- Network cableの整理
- ETMYのピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools