Differences between revisions 224 and 286 (spanning 62 versions)
Revision 224 as of 2017-12-27 09:25:56
Size: 7733
Comment:
Revision 286 as of 2018-02-05 11:40:08
Size: 8488
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/2/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}}
Line 17: Line 17:
* 責任者
  * Green setting on PR2:
   * 12/26 *Akutsu, Yokogawa + 1 or 2
   * 12/27 *Yokogawa + 1 or 2
 * *: responsible person

 * Beam leading to REFP port
  * *Izumi
Line 54: Line 54:
2017/12/27(Wed.) 2017/2/5(Mon.)
Line 56: Line 56:
 * Remote participants by educe: None  * Remote participants by eZuce: Takahashi, Aso
Line 58: Line 58:
 * 停電からの復帰関連
  * DGS: PR3以外は全て復帰した。
  * AEL: PR2とIOOの電源を分けた。復電後24V
  * IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。
   * TTFSSも確認できていない。
   * MCも復帰できていない。
  * Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。
   * PRMのみ少しキックがあった。大きさは数十uradくらい。
  * Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。
  * 真空: MCポンプのみ復帰。腕はそのまま。
 * Report of work (*:responsible person)
  * Vibration Isolation,
   * Restarted the BS realtime model.

  * Alignment: Izumi, Okutomi
   * ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
    * For vertical, below BF transfer function seems to be OK.
    * Yaw might be rotating too much.
     * After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much.
Line 70: Line 69:
 * Report of work (*:responsible person)  * Work plan (*:responsible person)
Line 72: Line 71:
  * AOS: *Akutsu
   * PR2の横にグリーンを構築しつつある。
    * 今日はビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。
  * Alignment: *Izumi, Okutomi
    * We will rotate IP yaw to release somewhere touching. This work takes 1day at least.
    * Detchar for spectrum of suspension is necessary as soon as possible.
Line 78: Line 75:
 * IOO: ISS準備と実験。   * Vacuum
    * Gate valve will be closed today.
    * Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks.
 
  * Type B
   * SR assembly continues.
Line 80: Line 82:
 * Current limitを変更した。IOOは18A、その他は21Aに設定した。
 


 
  * Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa
   * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。

 * Work plan (*:responsible person)
  * AOS: *Akutsu
   * グリーンのビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。



 * Laser hazard
   * センターはSR奥がハザードエリア。
 * Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it.
Line 100: Line 85:

  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。

 * Week of 12/25
  * Planed power outage in the afternoon on 12/25.
  * Week of 2/5
   * Finding causes of ETMY trouble.
    * Evacuation might be needed if ETMY is touching somewhere.
    * Cooling also will be delayed for 2weeks or so.
Line 111: Line 91:
  * k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい   * The ETMY mirror showed a strange scattering pattern.
Line 123: Line 103:
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 131: Line 116:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 138: Line 123:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/5 updated KAGRA/Commissioning/Commissioning_schedule_20180206.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/5(Mon.)

  • Remote participants by eZuce: Takahashi, Aso
  • Report of work (*:responsible person)
    • Vibration Isolation,
      • Restarted the BS realtime model.
    • Alignment: Izumi, Okutomi
      • ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
        • For vertical, below BF transfer function seems to be OK.
        • Yaw might be rotating too much.
          • After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much.
  • Work plan (*:responsible person)
    • Alignment: *Izumi, Okutomi
      • We will rotate IP yaw to release somewhere touching. This work takes 1day at least.
      • Detchar for spectrum of suspension is necessary as soon as possible.
    • Vacuum
      • Gate valve will be closed today.
      • Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks.
    • Type B
      • SR assembly continues.
  • Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it.
  • Weekly
    • Week of 2/5
      • Finding causes of ETMY trouble.
        • Evacuation might be needed if ETMY is touching somewhere.
        • Cooling also will be delayed for 2weeks or so.
  • Issues
    • The ETMY mirror showed a strange scattering pattern.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)