Differences between revisions 224 and 293 (spanning 69 versions)
Revision 224 as of 2017-12-27 09:25:56
Size: 7733
Comment:
Revision 293 as of 2018-02-09 09:09:28
Size: 7878
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/2/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}}
Line 17: Line 17:
* 責任者
  * Green setting on PR2:
   * 12/26 *Akutsu, Yokogawa + 1 or 2
   * 12/27 *Yokogawa + 1 or 2
 * *: responsible person

 * Beam leading to REFP port
  * *Izumi
Line 54: Line 54:
2017/12/27(Wed.) 2017/2/9(Fri.)
Line 56: Line 56:
 * Remote participants by educe: None

 * 停電からの復帰関連
  * DGS: PR3以外は全て復帰した。
  * AEL: PR2とIOOの電源を分けた。復電後24V
  * IOO: 回路が壊れているかどうかはまだ確認出来ていない。コモンモード回路のAOMのオフセットが出ないことがすでに判明。
   * TTFSSも確認できていない。
   * MCも復帰できていない。
  * Type Bp: PR3以外、BSも含めて動いている模様。Oplevも復帰。PRMは伝達関数もほぼ測定した。
   * PRMのみ少しキックがあった。大きさは数十uradくらい。
  * Type A: Xendはほぼ復帰した。Yendは復電後、そのまま。
  * 真空: MCポンプのみ復帰。腕はそのまま。
 * Remote participants by eZuce: None
Line 71: Line 59:
  * Alignment and Vibration Isolation: *Miyakawa
   * Drift by cooling is small.
Line 72: Line 62:
  * AOS: *Akutsu
   * PR2の横にグリーンを構築しつつある。
    * 今日はビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。

 * IOO: ISS準備と実験。

 * Current limitを変更した。IOOは18A、その他は21Aに設定した。
 


 
  * Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa
   * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。
  * Cooling: *Kimura, Suzuki, Yokozawa, Aso, Miyakawa, Miyamoto
   * One of the cooled was stopped due to the leak of water. This will be fixed in the next week. It does not affect the schedule of cooling. (Kimura)
   * PLC values are fixed. Power cable on the wall once accidentally might be unplugged and plugged, then PC was not turned on. (Aso)
   * Some of the temperature channels have been fixed. (Miyakawa, Miyamoto, Yokozawa)
Line 89: Line 68:
  * AOS: *Akutsu
   * グリーンのビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。
Line 94: Line 69:


 * Laser hazard
   * センターはSR奥がハザードエリア。
 * Laser hazard: PSL room in the morning. IMM in the afternoon.
Line 100: Line 72:

  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。

 * Week of 12/25
  * Planed power outage in the afternoon on 12/25.
  * Week of 2/5
    * 2/7 Cooling.
Line 111: Line 77:
  * k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい
Line 123: Line 89:
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 131: Line 102:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 138: Line 109:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/5 updated KAGRA/Commissioning/Commissioning_schedule_20180206.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/9(Fri.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and Vibration Isolation: *Miyakawa
      • Drift by cooling is small.
    • Cooling: *Kimura, Suzuki, Yokozawa, Aso, Miyakawa, Miyamoto
      • One of the cooled was stopped due to the leak of water. This will be fixed in the next week. It does not affect the schedule of cooling. (Kimura)
      • PLC values are fixed. Power cable on the wall once accidentally might be unplugged and plugged, then PC was not turned on. (Aso)
      • Some of the temperature channels have been fixed. (Miyakawa, Miyamoto, Yokozawa)
  • Work plan (*:responsible person)
  • Laser hazard: PSL room in the morning. IMM in the afternoon.
  • Weekly
    • Week of 2/5
      • 2/7 Cooling.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)