Line 11: | Line 11: |
2017/1/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180109.png||width=1200}} |
2017/2/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Beam leading to REFP port * *Izumi |
Line 51: | Line 54: |
2017/1/10(Wed.) | 2017/2/5(Mon.) |
Line 53: | Line 56: |
* 12時半よりファン小屋で真空と低温の細かい打ち合わせ。 * Remote participants by educe: None |
* Remote participants by eZuce: Takahashi, Aso |
Line 58: | Line 59: |
* Vibration Isolation, * Restarted the BS realtime model. * Alignment: Izumi, Okutomi * ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere. * For vertical, below BF transfer function seems to be OK. * Yaw might be rotating too much. * After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much. |
|
Line 61: | Line 71: |
* Alignment: *Izumi, Okutomi * We will rotate IP yaw to release somewhere touching. This work takes 1day at least. * Detchar for spectrum of suspension is necessary as soon as possible. |
|
Line 62: | Line 75: |
* Laser hazard * センターはIMM奥がハザードエリア。 |
* Vacuum * Gate valve will be closed today. * Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks. * Type B * SR assembly continues. * Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it. |
Line 66: | Line 85: |
* Week of 1/8 * vacuum meeting 12:30 on 1/10, at fan hut. * Re-alignment for IFO on 1/11, 12. * Damping for ETMY on 1/13, 14. * Week of 1/15 * IOO works. * Pump down, leak check in the later of this week. |
* Week of 2/5 * Finding causes of ETMY trouble. * Evacuation might be needed if ETMY is touching somewhere. * Cooling also will be delayed for 2weeks or so. |
Line 76: | Line 91: |
* The ETMY mirror showed a strange scattering pattern. | |
Line 88: | Line 103: |
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || |
|
Line 97: | Line 116: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 104: | Line 123: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/5(Mon.)
- Remote participants by eZuce: Takahashi, Aso
- Report of work (*:responsible person)
- Vibration Isolation,
- Restarted the BS realtime model.
- Alignment: Izumi, Okutomi
- ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
- For vertical, below BF transfer function seems to be OK.
- Yaw might be rotating too much.
- After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much.
- ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
- Vibration Isolation,
- Work plan (*:responsible person)
- Alignment: *Izumi, Okutomi
- We will rotate IP yaw to release somewhere touching. This work takes 1day at least.
- Detchar for spectrum of suspension is necessary as soon as possible.
- Vacuum
- Gate valve will be closed today.
- Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks.
- Type B
- SR assembly continues.
- Alignment: *Izumi, Okutomi
- Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it.
- Weekly
- Week of 2/5
- Finding causes of ETMY trouble.
- Evacuation might be needed if ETMY is touching somewhere.
- Cooling also will be delayed for 2weeks or so.
- Finding causes of ETMY trouble.
- Week of 2/5
- Issues
- The ETMY mirror showed a strange scattering pattern.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools