Differences between revisions 241 and 277 (spanning 36 versions)
Revision 241 as of 2018-01-10 16:18:14
Size: 6959
Comment:
Revision 277 as of 2018-01-31 09:17:59
Size: 8057
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
2017/1/30 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/11 *Izumi, Nagano, Shimoda
  * 1/12 *Izumi, Nagano, Shimoda
Line 22: Line 19:
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
 * Beam leading to REFP port
  * *Izumi
Line 61: Line 54:
2017/1/10(Wed.) 2017/1/31(Wed.)
Line 63: Line 56:
 * 12時半よりファン小屋で真空と低温の細かい打ち合わせ。

* Remote participants by educe: None
 * Remote participants by eZuce: Miyoki
Line 68: Line 59:
  * Vacuum:
   * Leakが三箇所でみつかった。一つは増し締めで解決。もう二つは高真空でのリークなので、今回はそのまま。
   * 真空の判断でゲートバルブを開ける。

  * Alignment
   * 1日の揺れが線形領域内の半分程度に収まった。Excitationが以前収まらない。
Line 70: Line 67:
  * Vacuum: *木村、上田、宍戸、高橋
   * 今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。
   * gate valveを開ける。

  * IOO: *苔山
   * 今日一日光を使う。

  * Alignment: *和泉
   * 今日の夕方、全員が出坑してから。

  * 機器制御のチェック: *麻生、日立造船
Line 72: Line 80:
 * Laser hazard
  * センターはIMM奥がハザードエリア。
 * Laser hazard: IMMTより上流、夕方全員が出てからSR2-3ラインより奥。
Line 76: Line 83:
  * Week of 1/8
   * vacuum meeting 12:30 on 1/10, at fan hut.
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.
Line 81: Line 84:
  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.
  * Week of 1/29
   * 1/29,30 leak check.
   * 1/31 Opening ETMY gate valve.
   * 1/31-2/2 Re-checking main beam to ETMY

  * Week of 2/5
   * 2/5 Cooling start.
Line 86: Line 94:
  * Network cableの整理
Line 98: Line 106:
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
Line 108: Line 118:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 115: Line 125:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])  * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/30 updated KAGRA/Commissioning/Commissioning_schedule_20180130.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/31(Wed.)

  • Remote participants by eZuce: Miyoki
  • Report of work (*:responsible person)
    • Vacuum:
      • Leakが三箇所でみつかった。一つは増し締めで解決。もう二つは高真空でのリークなので、今回はそのまま。
      • 真空の判断でゲートバルブを開ける。
    • Alignment
      • 1日の揺れが線形領域内の半分程度に収まった。Excitationが以前収まらない。
  • Work plan (*:responsible person)
    • Vacuum: *木村、上田、宍戸、高橋
      • 今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。
      • gate valveを開ける。
    • IOO: *苔山
      • 今日一日光を使う。
    • Alignment: *和泉
      • 今日の夕方、全員が出坑してから。
    • 機器制御のチェック: *麻生、日立造船
  • Laser hazard: IMMTより上流、夕方全員が出てからSR2-3ラインより奥。
  • Weekly
    • Week of 1/29
      • 1/29,30 leak check.
      • 1/31 Opening ETMY gate valve.
      • 1/31-2/2 Re-checking main beam to ETMY
    • Week of 2/5
      • 2/5 Cooling start.
  • Issues
    • Network cableの整理

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)