Differences between revisions 241 and 280 (spanning 39 versions)
Revision 241 as of 2018-01-10 16:18:14
Size: 6959
Comment:
Revision 280 as of 2018-02-01 09:17:23
Size: 9183
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
2017/1/30 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/11 *Izumi, Nagano, Shimoda
  * 1/12 *Izumi, Nagano, Shimoda
Line 22: Line 19:
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
 * Beam leading to REFP port
  * *Izumi
Line 61: Line 54:
2017/1/10(Wed.) 2017/2/1(Thur.)
Line 63: Line 56:
 * 12時半よりファン小屋で真空と低温の細かい打ち合わせ。

* Remote participants by educe: None
 * Remote participants by eZuce: None
Line 68: Line 59:
  * Vacuum: 木村
   * Gage valveが空いた。真空度はざっくりArm:1e-6 Cryo:1e-4で、徐々に平衡状態になっている。
   * EYVの6本のピストンのうちの3本をリリースして防振系をフリーにしようとしたが、結局フリーにはならず、2mm下がって、0.5mm戻した。しばらくは現状のまま行く。来週もう一度トライ。。

  * Alignment: 和泉、桐井、道村、奥富
   * Glitchの原因がどうやらLVDT関連の電気系である可能性が高まった。すくなくともメカ系ではなさそう。
   * LVDTのDACにオフセットを加えると現れる。
   * エンドでのビームはシャッターを開けたらすぐにETMYには届いたが、ゲートバルブが空いていなかったようで、バッフルPDに光が届かなかった。BSには光は返ってきた。
   * BSに光を返すとOplevで見てYawに線形領域を超えるくらいずれていた。

  * 機器制御のチェック: *麻生、日立造船
   * センター、各エンド64chが使えるようになった。
Line 70: Line 74:
  * Vacuum: *木村、上田、宍戸、高橋
   * ゲートバルブにまずgate valveを開け、その後今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。

  * IOO: *苔山
   * 今日一日光を使う。

  * Alignment: *和泉
   * 今日の夕方、全員が出坑してからバッフルPDのチェック。
   * 午後にOplevの再センタリングをしたい。

  * WAB: *阿久津
   * 作業と重なるのでビームをできるだけ避けてほしい。

  * Type B
   * Blade inspection.
   * Re-centering oplev.

 * Laser hazard: 現在PSL。今日は午後のある時点でアラインメントのためSR2-3ラインより奥に変更。アラインメント完了後、PSLに戻す。

 * Weekly

  * Week of 1/29
   * 1/31-2/2 Re-checking main beam to ETMY

  * Week of 2/5
   * 2/5 Cooling start.
Line 72: Line 102:
 * Laser hazard
  * センターはIMM奥がハザードエリア。

 * Weekly
  * Week of 1/8
   * vacuum meeting 12:30 on 1/10, at fan hut.
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.

  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.
Line 86: Line 103:
  * Network cableの整理
  * EYVの足のリリースで防振系がフリーにはならない。
  * Leakが二箇所残っている。
Line 98: Line 117:
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
Line 108: Line 129:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 115: Line 136:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])  * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/30 updated KAGRA/Commissioning/Commissioning_schedule_20180130.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/1(Thur.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Vacuum: 木村
      • Gage valveが空いた。真空度はざっくりArm:1e-6 Cryo:1e-4で、徐々に平衡状態になっている。

      • EYVの6本のピストンのうちの3本をリリースして防振系をフリーにしようとしたが、結局フリーにはならず、2mm下がって、0.5mm戻した。しばらくは現状のまま行く。来週もう一度トライ。。
    • Alignment: 和泉、桐井、道村、奥富
      • Glitchの原因がどうやらLVDT関連の電気系である可能性が高まった。すくなくともメカ系ではなさそう。
      • LVDTのDACにオフセットを加えると現れる。
      • エンドでのビームはシャッターを開けたらすぐにETMYには届いたが、ゲートバルブが空いていなかったようで、バッフルPDに光が届かなかった。BSには光は返ってきた。
      • BSに光を返すとOplevで見てYawに線形領域を超えるくらいずれていた。
    • 機器制御のチェック: *麻生、日立造船
      • センター、各エンド64chが使えるようになった。
  • Work plan (*:responsible person)
    • Vacuum: *木村、上田、宍戸、高橋
      • ゲートバルブにまずgate valveを開け、その後今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。
    • IOO: *苔山
      • 今日一日光を使う。
    • Alignment: *和泉
      • 今日の夕方、全員が出坑してからバッフルPDのチェック。
      • 午後にOplevの再センタリングをしたい。
    • WAB: *阿久津
      • 作業と重なるのでビームをできるだけ避けてほしい。
    • Type B
      • Blade inspection.
      • Re-centering oplev.
  • Laser hazard: 現在PSL。今日は午後のある時点でアラインメントのためSR2-3ラインより奥に変更。アラインメント完了後、PSLに戻す。
  • Weekly
    • Week of 1/29
      • 1/31-2/2 Re-checking main beam to ETMY
    • Week of 2/5
      • 2/5 Cooling start.
  • Issues
    • Network cableの整理
    • EYVの足のリリースで防振系がフリーにはならない。
    • Leakが二箇所残っている。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)