Line 11: | Line 11: |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/1/30 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/11 *Izumi * 1/12 *Izumi |
|
Line 22: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 61: | Line 54: |
2017/1/11(Thrs.) | 2017/1/31(Wed.) |
Line 63: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: Miyoki |
Line 66: | Line 59: |
* Vacuum: 木村 * Leakが三箇所でみつかった。一つは増し締めで解決。もう二つは高真空でのリークなので、今回はそのまま。 * 真空の判断でゲートバルブを開ける。 * Alignment: 宮川 * 1日の揺れが線形領域内の半分程度に収まった。Excitationが以前収まらない。 |
|
Line 68: | Line 67: |
* Alignment: *Izumi * Oplev, Re-alignment |
* Vacuum: *木村、上田、宍戸、高橋 * 今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。 * gate valveを開ける。 |
Line 71: | Line 71: |
* Check of PLC at Yend for connection to measurement tools: Aso | * IOO: *苔山 * 今日一日光を使う。 |
Line 73: | Line 74: |
* Marionet Oplev: Akutsu * Laser hazard area * Behind of BS and SR line and Yend 1F |
* Alignment: *和泉 * 今日の夕方、全員が出坑してからバッフルPDのチェック。 * 機器制御のチェック: *麻生、日立造船 * Laser hazard: IMMTより上流、夕方全員が出てからSR2-3ラインより奥。 |
Line 79: | Line 83: |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. * Week of 1/15 * IOO works. * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. |
|
Line 91: | Line 85: |
* 1/29 Cooling start | * 1/29,30 leak check. * 1/31 Opening ETMY gate valve. * 1/31-2/2 Re-checking main beam to ETMY * Week of 2/5 * 2/5 Cooling start. |
Line 94: | Line 94: |
* Network cableの整理 | |
Line 106: | Line 106: |
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 116: | Line 118: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 123: | Line 125: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/30 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/31(Wed.)
- Remote participants by eZuce: Miyoki
- Report of work (*:responsible person)
- Vacuum: 木村
- Leakが三箇所でみつかった。一つは増し締めで解決。もう二つは高真空でのリークなので、今回はそのまま。
- 真空の判断でゲートバルブを開ける。
- Alignment: 宮川
- 1日の揺れが線形領域内の半分程度に収まった。Excitationが以前収まらない。
- Vacuum: 木村
- Work plan (*:responsible person)
- Vacuum: *木村、上田、宍戸、高橋
- 今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。
- gate valveを開ける。
- IOO: *苔山
- 今日一日光を使う。
- Alignment: *和泉
- 今日の夕方、全員が出坑してからバッフルPDのチェック。
- 機器制御のチェック: *麻生、日立造船
- Vacuum: *木村、上田、宍戸、高橋
- Laser hazard: IMMTより上流、夕方全員が出てからSR2-3ラインより奥。
- Weekly
- Week of 1/29
- 1/29,30 leak check.
- 1/31 Opening ETMY gate valve.
- 1/31-2/2 Re-checking main beam to ETMY
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/29
- Issues
- Network cableの整理
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools