7218
Comment:
|
7761
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/16 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/16(Tue.) | 2017/1/29(Mon.) |
Line 62: | Line 56: |
* Remote participants by educe: Inoue | * Remote participants by eZuce: Izumi |
Line 65: | Line 59: |
* Alignment: *Izumi * Baffle PDを入れるので、その回路を用意している。Oplev回路を改造してつかう。 |
|
Line 68: | Line 60: |
* BS: 新井 * L2Pをフィルターを設計した。DCもそこそ、高周波もかなりいったが、すごく低い周波数はもう少し改良する必要がある。 |
* Alignment * Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百urad)でドリフトがあるもようだが、範囲は狭まって来ている。Excitationの頻度が大きい。 * IOO: PMCをインストールして光学定盤に置いた。 * WAB: 物が入って、機械的に設計通りに動きそうかのチェック。 |
Line 72: | Line 67: |
* Alignment: *Izumi * EYでものの準備など。 |
* Vacuum: leak check * Alignment: Oplevのセンタリング。 |
Line 75: | Line 70: |
* Laser hazard: Upstream of IMM line. |
* Laser hazard: PSL area |
Line 79: | Line 74: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. |
|
Line 89: | Line 76: |
* 1/29 Cooling start | * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. * 1/30-2/2 Re-checking main beam to ETMY * Week of 2/5 * 2/5 Cooling start. |
Line 93: | Line 85: |
* Network cableの整理 * ピコモーターの反応がなくなる。 |
|
Line 104: | Line 98: |
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 114: | Line 110: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 121: | Line 117: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/29(Mon.)
- Remote participants by eZuce: Izumi
- Report of work (*:responsible person)
- Alignment
- Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百urad)でドリフトがあるもようだが、範囲は狭まって来ている。Excitationの頻度が大きい。
- IOO: PMCをインストールして光学定盤に置いた。
- WAB: 物が入って、機械的に設計通りに動きそうかのチェック。
- Alignment
- Work plan (*:responsible person)
- Vacuum: leak check
- Alignment: Oplevのセンタリング。
- Laser hazard: PSL area
- Weekly
- Week of 1/29
- 1/29,30 leak check.
- 1/30 Opening ETMY gate valve.
- 1/30-2/2 Re-checking main beam to ETMY
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/29
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools