Line 11: | Line 11: |
2017/1/16 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/17(Wed.) | 2017/1/29(Mon.) |
Line 62: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: Izumi |
Line 65: | Line 59: |
* Alignment: *Izumi * Buffle PDがETMYにインストールされた。真空槽内はケーブリングも含めて完了。 * 読み出し回路を用意している。ケーブルなどと合わせてほぼ準備が整った。計算機側の準備もOK。接続を待つのみ。 |
|
Line 69: | Line 60: |
* IOO * PSL上のパワーを変更して、メインパワーを1Wまで上げた。実際には干渉計直前で蹴っているので、干渉計側には今まで通り100mW程度が入っている。メインパワーの変動が数十%と大きくなってしまっている。今の所変動の原因は不明。 |
* Alignment * Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百urad)でドリフトがあるもようだが、範囲は狭まって来ている。Excitationの頻度が大きい。 * IOO: PMCをインストールして光学定盤に置いた。 * WAB: 物が入って、機械的に設計通りに動きそうかのチェック。 |
Line 73: | Line 67: |
* Alignment: *Izumi * 午前中EYでの回路接続。夕方から全域をハザートエリアにして、アラインメント作業。 |
* Vacuum: leak check * Alignment: Oplevのセンタリング。 |
Line 76: | Line 70: |
* Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment. | * Laser hazard: PSL area |
Line 80: | Line 74: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. |
|
Line 90: | Line 76: |
* 1/29 Cooling start | * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. * 1/30-2/2 Re-checking main beam to ETMY * Week of 2/5 * 2/5 Cooling start. |
Line 95: | Line 86: |
* ピコモーターの反応がなくなる。 | |
Line 106: | Line 98: |
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 116: | Line 110: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 123: | Line 117: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/29(Mon.)
- Remote participants by eZuce: Izumi
- Report of work (*:responsible person)
- Alignment
- Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百urad)でドリフトがあるもようだが、範囲は狭まって来ている。Excitationの頻度が大きい。
- IOO: PMCをインストールして光学定盤に置いた。
- WAB: 物が入って、機械的に設計通りに動きそうかのチェック。
- Alignment
- Work plan (*:responsible person)
- Vacuum: leak check
- Alignment: Oplevのセンタリング。
- Laser hazard: PSL area
- Weekly
- Week of 1/29
- 1/29,30 leak check.
- 1/30 Opening ETMY gate valve.
- 1/30-2/2 Re-checking main beam to ETMY
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/29
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools