Differences between revisions 259 and 285 (spanning 26 versions)
Revision 259 as of 2018-01-18 15:54:04
Size: 8831
Comment:
Revision 285 as of 2018-02-05 11:39:50
Size: 8489
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
2017/1/30 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/12 *Izumi
Line 21: Line 19:
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
 * Beam leading to REFP port
  * *Izumi
Line 60: Line 54:
2017/1/18(Thur.) 2017/2/5(Mon.)
Line 62: Line 56:
 * Remote participants by educe: None  * Remote participants by eZuce: Takahashi, Aso
Line 65: Line 59:
  * Alignment: *Izumi
   * EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。
   * ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。
   * CryopayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。
  * Vibration Isolation,
   * Restarted the BS realtime model.

  * Alignment: Izumi, Okutomi
   * ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
    * For vertical, below BF transfer function seems to be OK.
    * Yaw might be rotating too much.
     * After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much.
Line 71: Line 70:
  * Alignment: *Izumi
   * 午後3時か4時頃から、再度ゲインを上げてETMYでの確認を試す。
   * CryopayloadのVisual inspection.
   * φ800フランジは今日は開けておく。明日閉める。
Line 76: Line 71:
  * IOO: *Kokeyama
   * 1WをMCに入れる。
  * Alignment: *Izumi, Okutomi
    * We will rotate IP yaw to release somewhere touching. This work takes 1day at least.
    * Detchar for spectrum of suspension is necessary as soon as possible.
Line 79: Line 75:
  * 真空引き判断
   * チェックリスト最終確認。
   * 最速で今日の夕方ETMYで光が見えて、うまくいけばBSでもすぐに見える。
   * おそらくビームがBSまで返って届いているかの判断は明日朝になりそう。ただしリモートで全てできることなので、ビーム確認なしで真空引きをする可能性もある。
   * Cryostatのタッチがないかを確認。
   * φ800フランジを閉める。
  * Vacuum
    * Gate valve will be closed today.
    * Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks.
 
  * Type B
   * SR assembly continues.
Line 86: Line 82:
   * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.  * Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it.
Line 90: Line 85:
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
   * 1/19: Pump down.

  * Week of 1/22
   * 1/24,25 leak check.

  * Week of 1/29
   * 1/29 Cooling start
  * Week of 2/5
   * Finding causes of ETMY trouble.
    * Evacuation might be needed if ETMY is touching somewhere.
    * Cooling also will be delayed for 2weeks or so.
Line 104: Line 91:
  * Network cableの整理
  * Cryostatがタッチしている可能性あり。
  * ビームアラインメントの最終確認が時間的にぎりぎり。
  * The ETMY mirror showed a strange scattering pattern.
Line 118: Line 103:
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
Line 129: Line 116:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/30 updated KAGRA/Commissioning/Commissioning_schedule_20180130.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/5(Mon.)

  • Remote participants by eZuce: Takahashi, Aso
  • Report of work (*:responsible person)
    • Vibration Isolation,
      • Restarted the BS realtime model.
    • Alignment: Izumi, Okutomi
      • ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
        • For vertical, below BF transfer function seems to be OK.
        • Yaw might be rotating too much.
          • After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much.
  • Work plan (*:responsible person)
    • Alignment: *Izumi, Okutomi
      • We will rotate IP yaw to release somewhere touching. This work takes 1day at least.
      • Detchar for spectrum of suspension is necessary as soon as possible.
    • Vacuum
      • Gate valve will be closed today.
      • Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks.
    • Type B
      • SR assembly continues.
  • Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it.
  • Weekly
    • Week of 2/5
      • Finding causes of ETMY trouble.
        • Evacuation might be needed if ETMY is touching somewhere.
        • Cooling also will be delayed for 2weeks or so.
  • Issues
    • The ETMY mirror showed a strange scattering pattern.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)