Differences between revisions 266 and 286 (spanning 20 versions)
Revision 266 as of 2018-01-23 09:15:13
Size: 7734
Comment:
Revision 286 as of 2018-02-05 11:40:08
Size: 8488
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
2017/2/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}}
Line 18: Line 18:

 * Pump down
  * 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 57: Line 54:
2017/1/23(Tue.) 2017/2/5(Mon.)
Line 59: Line 56:
 * Remote participants by educe: Aso  * Remote participants by eZuce: Takahashi, Aso
Line 62: Line 59:
  * None   * Vibration Isolation,
   * Restarted the BS realtime model.

  * Alignment: Izumi, Okutomi
   * ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
    * For vertical, below BF transfer function seems to be OK.
    * Yaw might be rotating too much.
     * After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much.
Line 65: Line 70:

  * Alignment: *Izumi, Okutomi
    * We will rotate IP yaw to release somewhere touching. This work takes 1day at least.
    * Detchar for spectrum of suspension is necessary as soon as possible.
Line 66: Line 76:
   * 本日午後真空引き予定
    * ETMY立会い: 木村、鈴木、都丸、横澤、高橋(センター)、阿久津(センター)、宮川
    * コントロールルーム: 和泉、奥富
   * φ800フランジ締め
   * dial gaugeセット
   * Oplev確認
   * Tcam確認
   * Check listによる最終確認
    * Gate valve will be closed today.
    * Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks.
 
  * Type B
   * SR assembly continues.
Line 75: Line 82:
 * IOO: 苔山
  * 午後にTilt sensorやPMCなどの作業あり。

  * Alignment: *Izumi
   * BS modelのテコ入れ: Izumi

 * Laser hazard: 今日は午前はPSL、午後からIMM、夕方から夜間にかけて全域。
 * Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it.
Line 84: Line 85:
  * Week of 1/22
   * 1/23: Pump down.
   * 1/24: Turbo pump on.

  * Week of 1/29
   * 1/29,30 leak check.
Line 92: Line 86:
   * 2/5 Cooling start.
   * Finding causes of ETMY trouble.
    * Evacuation might be needed if ETMY is touching somewhere.
    * Cooling also will be delayed for 2weeks or so.
Line 96: Line 91:
  * Network cableの整理   * The ETMY mirror showed a strange scattering pattern.
Line 108: Line 103:
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
Line 119: Line 116:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/5 updated KAGRA/Commissioning/Commissioning_schedule_20180206.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/5(Mon.)

  • Remote participants by eZuce: Takahashi, Aso
  • Report of work (*:responsible person)
    • Vibration Isolation,
      • Restarted the BS realtime model.
    • Alignment: Izumi, Okutomi
      • ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
        • For vertical, below BF transfer function seems to be OK.
        • Yaw might be rotating too much.
          • After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much.
  • Work plan (*:responsible person)
    • Alignment: *Izumi, Okutomi
      • We will rotate IP yaw to release somewhere touching. This work takes 1day at least.
      • Detchar for spectrum of suspension is necessary as soon as possible.
    • Vacuum
      • Gate valve will be closed today.
      • Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks.
    • Type B
      • SR assembly continues.
  • Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it.
  • Weekly
    • Week of 2/5
      • Finding causes of ETMY trouble.
        • Evacuation might be needed if ETMY is touching somewhere.
        • Cooling also will be delayed for 2weeks or so.
  • Issues
    • The ETMY mirror showed a strange scattering pattern.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)