7734
Comment:
|
8488
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/18 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/2/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}} |
Line 18: | Line 18: |
* Pump down * 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
|
Line 57: | Line 54: |
2017/1/23(Tue.) | 2017/2/5(Mon.) |
Line 59: | Line 56: |
* Remote participants by educe: Aso | * Remote participants by eZuce: Takahashi, Aso |
Line 62: | Line 59: |
* None | * Vibration Isolation, * Restarted the BS realtime model. * Alignment: Izumi, Okutomi * ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere. * For vertical, below BF transfer function seems to be OK. * Yaw might be rotating too much. * After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much. |
Line 65: | Line 70: |
* Alignment: *Izumi, Okutomi * We will rotate IP yaw to release somewhere touching. This work takes 1day at least. * Detchar for spectrum of suspension is necessary as soon as possible. |
|
Line 66: | Line 76: |
* 本日午後真空引き予定 * ETMY立会い: 木村、鈴木、都丸、横澤、高橋(センター)、阿久津(センター)、宮川 * コントロールルーム: 和泉、奥富 * φ800フランジ締め * dial gaugeセット * Oplev確認 * Tcam確認 * Check listによる最終確認 |
* Gate valve will be closed today. * Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks. * Type B * SR assembly continues. |
Line 75: | Line 82: |
* IOO: 苔山 * 午後にTilt sensorやPMCなどの作業あり。 * Alignment: *Izumi * BS modelのテコ入れ: Izumi * Laser hazard: 今日は午前はPSL、午後からIMM、夕方から夜間にかけて全域。 |
* Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it. |
Line 84: | Line 85: |
* Week of 1/22 * 1/23: Pump down. * 1/24: Turbo pump on. * Week of 1/29 * 1/29,30 leak check. |
|
Line 92: | Line 86: |
* 2/5 Cooling start. |
* Finding causes of ETMY trouble. * Evacuation might be needed if ETMY is touching somewhere. * Cooling also will be delayed for 2weeks or so. |
Line 96: | Line 91: |
* Network cableの整理 | * The ETMY mirror showed a strange scattering pattern. |
Line 108: | Line 103: |
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || |
|
Line 119: | Line 116: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/5(Mon.)
- Remote participants by eZuce: Takahashi, Aso
- Report of work (*:responsible person)
- Vibration Isolation,
- Restarted the BS realtime model.
- Alignment: Izumi, Okutomi
- ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
- For vertical, below BF transfer function seems to be OK.
- Yaw might be rotating too much.
- After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much.
- ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere.
- Vibration Isolation,
- Work plan (*:responsible person)
- Alignment: *Izumi, Okutomi
- We will rotate IP yaw to release somewhere touching. This work takes 1day at least.
- Detchar for spectrum of suspension is necessary as soon as possible.
- Vacuum
- Gate valve will be closed today.
- Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks.
- Type B
- SR assembly continues.
- Alignment: *Izumi, Okutomi
- Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it.
- Weekly
- Week of 2/5
- Finding causes of ETMY trouble.
- Evacuation might be needed if ETMY is touching somewhere.
- Cooling also will be delayed for 2weeks or so.
- Finding causes of ETMY trouble.
- Week of 2/5
- Issues
- The ETMY mirror showed a strange scattering pattern.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools