Differences between revisions 271 and 288 (spanning 17 versions)
Revision 271 as of 2018-01-29 08:57:23
Size: 7312
Comment:
Revision 288 as of 2018-02-06 10:06:40
Size: 8362
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/1/23 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
2017/2/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}}
Line 54: Line 54:
2017/1/29(Mon.) 2017/2/6(Tue.)
Line 56: Line 56:
 * Remote participants by eZuce: None  * Remote participants by eZuce: Takahashi
Line 59: Line 59:

  * Alignment
   * Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百mrad)でドリフトがあるもようだが、範囲は狭まって来ている。
  * Alignment and Vibration Isolation: Izumi, Okutomi
   * BF yaw transfer function showed that it did not move well. It was fount that the position of IP was different from when pumping down started.
   * IP drifted 2mm in the air, and another 2mm when pump down. (Takahashi)
   * ETMY IPs were set back to where they were on 1/13. The transfer function now has the similar shape as before, but the Q of lowest peak is a bit low.
Line 64: Line 65:
  * Vacuum: leak check
  * Alignment: Oplevのセンタリング。
Line 67: Line 66:
  * Alignment and Vibration Isolation: *Izumi
   * We can move moving masses of BF, or IPs of yaw to check TF can be recovered.
   * We will play one more day under vacuum.
Line 68: Line 70:
 * Laser hazard: Upstream of IMMT line   * Type A: *Yokozawa
   * RT model of Type A will be separated into cryopayload and tower.
 
  * Type B
   * SR assembly continues.

 * Laser hazard: PSL. Green might be used late of the afternoon, then the center area and Y end will be the hazard area.
Line 71: Line 79:

  * Week of 1/29
   * 1/29,30 leak check.
   * 1/30 Opening ETMY gate valve.
Line 77: Line 80:
   * 2/5 Cooling start.    * Finding causes of ETMY trouble.
    * Vent might be needed if ETMY is touching somewhere.
    * Cooling also will be delayed for 2weeks or so.
Line 81: Line 86:
  * Network cableの整理
  * ピコモーターの反応がなくなる。
  * IP drifted 2mm in the air, and another 2mm when pump down.
Line 94: Line 98:
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/5 updated KAGRA/Commissioning/Commissioning_schedule_20180206.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/6(Tue.)

  • Remote participants by eZuce: Takahashi
  • Report of work (*:responsible person)
    • Alignment and Vibration Isolation: Izumi, Okutomi
      • BF yaw transfer function showed that it did not move well. It was fount that the position of IP was different from when pumping down started.
      • IP drifted 2mm in the air, and another 2mm when pump down. (Takahashi)
      • ETMY IPs were set back to where they were on 1/13. The transfer function now has the similar shape as before, but the Q of lowest peak is a bit low.
  • Work plan (*:responsible person)
    • Alignment and Vibration Isolation: *Izumi
      • We can move moving masses of BF, or IPs of yaw to check TF can be recovered.
      • We will play one more day under vacuum.
    • Type A: *Yokozawa
      • RT model of Type A will be separated into cryopayload and tower.
    • Type B
      • SR assembly continues.
  • Laser hazard: PSL. Green might be used late of the afternoon, then the center area and Y end will be the hazard area.
  • Weekly
    • Week of 2/5
      • Finding causes of ETMY trouble.
        • Vent might be needed if ETMY is touching somewhere.
        • Cooling also will be delayed for 2weeks or so.
  • Issues
    • IP drifted 2mm in the air, and another 2mm when pump down.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)