8101
Comment:
|
7692
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/30 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}} |
2017/2/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}} |
Line 54: | Line 54: |
2017/1/31(Wed.) | 2017/2/8(Thur.) |
Line 59: | Line 59: |
* Vacuum: 木村 * Leakが三箇所でみつかった。一つは増し締めで解決。もう二つは高真空でのリークなので、今回はそのまま。 * 真空の判断でゲートバルブを開ける。 |
* Alignment and Vibration Isolation: Izumi, Miyakawa * Drift by cooling is smaller than that of pump down. |
Line 63: | Line 62: |
* Alignment: 宮川 * 1日の揺れが線形領域内の半分程度に収まった。Excitationが以前収まらない。 |
* Cooling: Kimura, Suzuki, Yokozawa * 4k cooler, 50k cooler started. * PLC values are not available. |
Line 67: | Line 68: |
* Vacuum: *木村、上田、宍戸、高橋 * 今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。 * gate valveを開ける。 |
* Alignment: Miyakawa * We keep the eye on the oplev response and correct the alignment if drift is much. |
Line 71: | Line 71: |
* IOO: *苔山 * 今日一日光を使う。 * Alignment: *和泉 * 今日の夕方、全員が出坑してからバッフルPDのチェック。 * 機器制御のチェック: *麻生、日立造船 * Laser hazard: IMMTより上流、夕方全員が出てからSR2-3ラインより奥。 |
* Laser hazard: All area related to inside the vacuum. |
Line 83: | Line 74: |
* Week of 1/29 * 1/29,30 leak check. * 1/31 Opening ETMY gate valve. * 1/31-2/2 Re-checking main beam to ETMY |
|
Line 90: | Line 75: |
* 2/5 Cooling start. | * 2/7 Cooling. |
Line 94: | Line 79: |
* Network cableの整理 | |
Line 106: | Line 91: |
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/8(Thur.)
- Remote participants by eZuce: Miyoki
- Report of work (*:responsible person)
- Alignment and Vibration Isolation: Izumi, Miyakawa
- Drift by cooling is smaller than that of pump down.
- Cooling: Kimura, Suzuki, Yokozawa
- 4k cooler, 50k cooler started.
- PLC values are not available.
- Alignment and Vibration Isolation: Izumi, Miyakawa
- Work plan (*:responsible person)
- Alignment: Miyakawa
- We keep the eye on the oplev response and correct the alignment if drift is much.
- Alignment: Miyakawa
- Laser hazard: All area related to inside the vacuum.
- Weekly
- Week of 2/5
- 2/7 Cooling.
- Week of 2/5
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)