Differences between revisions 281 and 289 (spanning 8 versions)
Revision 281 as of 2018-02-01 09:20:45
Size: 9179
Comment:
Revision 289 as of 2018-02-07 09:24:03
Size: 8366
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/1/30 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}}
2017/2/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}}
Line 54: Line 54:
2017/2/1(Thur.) 2017/2/7(Wed.)
Line 59: Line 59:
  * Vacuum: *木村、上田、宍戸、高橋
   * Gage valveが空いた。真空度はざっくりArm:1e-6 Cryo:1e-4で、徐々に平衡状態になっている。
   * EYVの6本のピストンのうちの3本をリリースして防振系をフリーにしようとしたが、結局フリーにはならず、2mm下がって、0.5mm戻した。しばらくは現状のまま行く。来週もう一度トライ。。
  * Alignment and Vibration Isolation: Izumi, Okutomi
   * Searching optimal position of IP of ETMY was successfully done. Stiffness is almost the same as what was measured in the air. But Q is still not so high. Still something lower stage might be hitting somewhere.
  * Mirror view by Team also moved by 6mm order! It means that the calibration can be wrong by 25 times.
  * The result of fine tuning showed 1mm off to -x direction.
Line 63: Line 64:
  * Alignment: 和泉、桐井、道村、奥富
   * Glitchの原因がどうやらLVDT関連の電気系である可能性が高まった。すくなくともメカ系ではなさそう。
    * LVDTのDACにオフセットを加えると現れる。
   * エンドでのビームはシャッターを開けたらすぐにETMYには届いたが、ゲートバルブが空いていなかったようで、バッフルPDに光が届かなかった。
    * BSにも光は返ってきた。
    * BSに光を返すとOplevで見てYawに線形領域を超えるくらいずれていた。

  * 機器制御のチェック: *麻生、日立造船
   * センター、各エンド64chが使えるようになった。
 * Vacuum: Kimura
  * Another leakage was found 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling.
Line 75: Line 68:
  * Vacuum: *和泉、早河
   * ゲートバルブにまずgate valveを開け、その後今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。
Line 78: Line 69:
  * IOO: *苔山
   * 今日一日光を使う。
  * Cooling: Kimura, Suzuki, Yokozawa
   * We will start cooling around 11AM.
Line 81: Line 72:
  * Alignment: *和泉
   * 午後にOplevの再センタリングをしたい。WABと時間調整。
  * WAB cooling test: Akutsu
   * Temperature monitors are being prepared.
   * Oplev is ready.
Line 84: Line 76:
  * WAB: *阿久津
   * 作業と重なるのでビームをできるだけ避けてほしい。アラインメントと時間調整。

  * Type B
   * Blade inspection.
   * Re-centering oplev.

 * Laser hazard: 現在PSL。今日は午後のある時点でアラインメントのためSR2-3ラインより奥に変更。アラインメント完了後、PSLに戻す。
 * Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area.
Line 94: Line 79:

  * Week of 1/29
   * 1/31-2/2 Re-checking main beam to ETMY
Line 99: Line 80:
   * 2/5 Cooling start.    * Finding causes of ETMY trouble.
    * Vent might be needed if ETMY is touching somewhere.
    * Cooling also will be delayed for 2weeks or so.
Line 103: Line 86:
  * Network cableの整理
  * EYVの足のリリースで防振系がフリーにはならない。
  * Leakが二箇所残っている。
  * IP drifted 2mm in the air, and another 2mm when pump down.
Line 117: Line 98:
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/5 updated KAGRA/Commissioning/Commissioning_schedule_20180206.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/7(Wed.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and Vibration Isolation: Izumi, Okutomi
      • Searching optimal position of IP of ETMY was successfully done. Stiffness is almost the same as what was measured in the air. But Q is still not so high. Still something lower stage might be hitting somewhere.
    • Mirror view by Team also moved by 6mm order! It means that the calibration can be wrong by 25 times.
    • The result of fine tuning showed 1mm off to -x direction.
  • Vacuum: Kimura
    • Another leakage was found 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling.
  • Work plan (*:responsible person)
    • Cooling: Kimura, Suzuki, Yokozawa
      • We will start cooling around 11AM.
    • WAB cooling test: Akutsu
      • Temperature monitors are being prepared.
      • Oplev is ready.
  • Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area.
  • Weekly
    • Week of 2/5
      • Finding causes of ETMY trouble.
        • Vent might be needed if ETMY is touching somewhere.
        • Cooling also will be delayed for 2weeks or so.
  • Issues
    • IP drifted 2mm in the air, and another 2mm when pump down.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)