Differences between revisions 288 and 289
Revision 288 as of 2018-02-06 10:06:40
Size: 8362
Comment:
Revision 289 as of 2018-02-07 09:24:03
Size: 8366
Comment:
Deletions are marked like this. Additions are marked like this.
Line 54: Line 54:
2017/2/6(Tue.) 2017/2/7(Wed.)
Line 56: Line 56:
 * Remote participants by eZuce: Takahashi  * Remote participants by eZuce: None
Line 60: Line 60:
   * BF yaw transfer function showed that it did not move well. It was fount that the position of IP was different from when pumping down started.
   * IP drifted 2mm in the air, and another 2mm when pump down. (Takahashi)
   * ETMY IPs were set back to where they were on 1/13. The transfer function now has the similar shape as before, but the Q of lowest peak is a bit low.
   * Searching optimal position of IP of ETMY was successfully done. Stiffness is almost the same as what was measured in the air. But Q is still not so high. Still something lower stage might be hitting somewhere.
  * Mirror view by Team also moved by 6mm order! It means that the calibration can be wrong by 25 times.
  * The result of fine tuning showed 1mm off to -x direction.

 * Vacuum: Kimura
  * Another leakage was found 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling.
Line 66: Line 69:
  * Alignment and Vibration Isolation: *Izumi
   * We can move moving masses of BF, or IPs of yaw to check TF can be recovered.
   * We will play one more day under vacuum.
  * Cooling: Kimura, Suzuki, Yokozawa
   * We will start cooling around 11AM.
Line 70: Line 72:
  * Type A: *Yokozawa
   * RT model of Type A will be separated into cryopayload and tower.
 
  * Type B
   * SR assembly continues.
  * WAB cooling test: Akutsu
   * Temperature monitors are being prepared.
   * Oplev is ready.
Line 76: Line 76:
 * Laser hazard: PSL. Green might be used late of the afternoon, then the center area and Y end will be the hazard area.  * Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area.

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/5 updated KAGRA/Commissioning/Commissioning_schedule_20180206.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/7(Wed.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and Vibration Isolation: Izumi, Okutomi
      • Searching optimal position of IP of ETMY was successfully done. Stiffness is almost the same as what was measured in the air. But Q is still not so high. Still something lower stage might be hitting somewhere.
    • Mirror view by Team also moved by 6mm order! It means that the calibration can be wrong by 25 times.
    • The result of fine tuning showed 1mm off to -x direction.
  • Vacuum: Kimura
    • Another leakage was found 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling.
  • Work plan (*:responsible person)
    • Cooling: Kimura, Suzuki, Yokozawa
      • We will start cooling around 11AM.
    • WAB cooling test: Akutsu
      • Temperature monitors are being prepared.
      • Oplev is ready.
  • Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area.
  • Weekly
    • Week of 2/5
      • Finding causes of ETMY trouble.
        • Vent might be needed if ETMY is touching somewhere.
        • Cooling also will be delayed for 2weeks or so.
  • Issues
    • IP drifted 2mm in the air, and another 2mm when pump down.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)