Comment:
|
9183
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
== Current task == | == Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/1/30 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}} |
Line 6: | Line 15: |
----- == Working people assignment == * *: responsible person * Beam leading to REFP port * *Izumi {{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} ----- <<Anchor(Meetings)>> ----- == Meetings == |
|
Line 7: | Line 47: |
== Meeting == === Weekly meeting === * Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokum Kaikan, or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
<<Anchor(MorningMeetings)>> |
Line 23: | Line 51: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 26: | Line 54: |
2017/10/10(Mon) | 2017/2/1(Thur.) |
Line 28: | Line 56: |
* Daily * 作業人員 * MIF: 苔山、横澤、新井、三代、和泉、中野、榎本 * Laser hazard: 川村 * 午前に各種準備で、午後からハザードエリア。 * 午後1時から2時まで見学があるので、午後3時頃からハザートエリア。 * 確認事項 * PRMは固定で進める、準備完了。 * k1pr0のIOシャーシを交換したので、問題があったら報告。 * PR2リモートテストも完了。順調。 * BS: あと少し。キャリブレーションなど。 * 先週の報告通りチェンバー中心からずれているが、そのまま進める。今日IMMT2でアラインメントをする。 * Gマット張り完了。 * BSの出口は塞いだままアラインメントを進める。 |
* Remote participants by eZuce: None * Report of work (*:responsible person) * Vacuum: 木村 * Gage valveが空いた。真空度はざっくりArm:1e-6 Cryo:1e-4で、徐々に平衡状態になっている。 * EYVの6本のピストンのうちの3本をリリースして防振系をフリーにしようとしたが、結局フリーにはならず、2mm下がって、0.5mm戻した。しばらくは現状のまま行く。来週もう一度トライ。。 * Alignment: 和泉、桐井、道村、奥富 * Glitchの原因がどうやらLVDT関連の電気系である可能性が高まった。すくなくともメカ系ではなさそう。 * LVDTのDACにオフセットを加えると現れる。 * エンドでのビームはシャッターを開けたらすぐにETMYには届いたが、ゲートバルブが空いていなかったようで、バッフルPDに光が届かなかった。BSには光は返ってきた。 * BSに光を返すとOplevで見てYawに線形領域を超えるくらいずれていた。 * 機器制御のチェック: *麻生、日立造船 * センター、各エンド64chが使えるようになった。 * Work plan (*:responsible person) * Vacuum: *木村、上田、宍戸、高橋 * ゲートバルブにまずgate valveを開け、その後今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。 * IOO: *苔山 * 今日一日光を使う。 * Alignment: *和泉 * 今日の夕方、全員が出坑してからバッフルPDのチェック。 * 午後にOplevの再センタリングをしたい。 * WAB: *阿久津 * 作業と重なるのでビームをできるだけ避けてほしい。 * Type B * Blade inspection. * Re-centering oplev. * Laser hazard: 現在PSL。今日は午後のある時点でアラインメントのためSR2-3ラインより奥に変更。アラインメント完了後、PSLに戻す。 |
Line 43: | Line 94: |
* 今週の目標はPR3からの光がBSまで届くこと。 * PRとBSの間のダクトをどうするかはクリーンネスの問題から、今日のweekly meetingで検討。 * PR側のアルミは使う人が各自外して使う。 * PR周りの測定をしたい。(大石) -> スケジュールを今日のweekly meetingで検討。 * 問題点など * 今日はアラインメントのタスクがMIF担当になっていて、作業する人はアサインされている。問題になったのは、責任者が決まっていなくて、入坑者の把握がまとまってできていない。入坑確認ことなどもあるので、タスク分担の分の現場の責任者を決めて入坑する人の取りまとめをする。 |
* Week of 1/29 * 1/31-2/2 Re-checking main beam to ETMY * Week of 2/5 * 2/5 Cooling start. * Issues * Network cableの整理 * EYVの足のリリースで防振系がフリーにはならない。 * Leakが二箇所残っている。 |
Line 53: | Line 110: |
---- <<Anchor(WeeklyMeetings)>> ==== Weekly meeting ==== * Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| ---- === Other meetings === * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] |
|
Line 55: | Line 145: |
----- | |
Line 57: | Line 147: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|Commissioning plan for Phase1]] | * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]] |
Line 61: | Line 151: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/30 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/1(Thur.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Vacuum: 木村
Gage valveが空いた。真空度はざっくりArm:1e-6 Cryo:1e-4で、徐々に平衡状態になっている。
- EYVの6本のピストンのうちの3本をリリースして防振系をフリーにしようとしたが、結局フリーにはならず、2mm下がって、0.5mm戻した。しばらくは現状のまま行く。来週もう一度トライ。。
- Alignment: 和泉、桐井、道村、奥富
- Glitchの原因がどうやらLVDT関連の電気系である可能性が高まった。すくなくともメカ系ではなさそう。
- LVDTのDACにオフセットを加えると現れる。
- エンドでのビームはシャッターを開けたらすぐにETMYには届いたが、ゲートバルブが空いていなかったようで、バッフルPDに光が届かなかった。BSには光は返ってきた。
- BSに光を返すとOplevで見てYawに線形領域を超えるくらいずれていた。
- 機器制御のチェック: *麻生、日立造船
- センター、各エンド64chが使えるようになった。
- Vacuum: 木村
- Work plan (*:responsible person)
- Vacuum: *木村、上田、宍戸、高橋
- ゲートバルブにまずgate valveを開け、その後今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。
- IOO: *苔山
- 今日一日光を使う。
- Alignment: *和泉
- 今日の夕方、全員が出坑してからバッフルPDのチェック。
- 午後にOplevの再センタリングをしたい。
- WAB: *阿久津
- 作業と重なるのでビームをできるだけ避けてほしい。
- Type B
- Blade inspection.
- Re-centering oplev.
- Vacuum: *木村、上田、宍戸、高橋
- Laser hazard: 現在PSL。今日は午後のある時点でアラインメントのためSR2-3ラインより奥に変更。アラインメント完了後、PSLに戻す。
- Weekly
- Week of 1/29
- 1/31-2/2 Re-checking main beam to ETMY
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/29
- Issues
- Network cableの整理
- EYVの足のリリースで防振系がフリーにはならない。
- Leakが二箇所残っている。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)