== Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/2/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}} ----- |
|
Line 4: | Line 17: |
* MIF * 10/13 苔山、*横澤、榎本、中野、三代、新井 . * 10/16 横澤、井上、榎本、*中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/17 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 . * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か |
* *: responsible person |
Line 19: | Line 19: |
. * 責任者 | * Beam leading to REFP port * *Izumi {{{#!wiki comment/dotted |
Line 21: | Line 24: |
<<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} ----- <<Anchor(Meetings)>> |
|
Line 25: | Line 47: |
<<Anchor(MorningMeetings)>> | |
Line 28: | Line 51: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 31: | Line 54: |
2017/10/13(Fri) | 2017/2/6(Tue.) |
Line 33: | Line 56: |
* Daily * 作業人員(*:責任者) * MIF: 苔山、*横澤、榎本、中野、三代、新井 |
* Remote participants by eZuce: Takahashi |
Line 37: | Line 58: |
* Laser hazard * PSLから15mWで、IMC入り口で10mW、PRM以降は1mW程度。今日のPR2の作業によって来週エンドをハザードエリアにするか決める。 * 来週以降も2mWでいこうと思っている。 |
* Report of work (*:responsible person) * Alignment and Vibration Isolation: Izumi, Okutomi * BF yaw transfer function showed that it did not move well. It was fount that the position of IP was different from when pumping down started. * IP drifted 2mm in the air, and another 2mm when pump down. (Takahashi) * ETMY IPs were set back to where they were on 1/13. The transfer function now has the similar shape as before, but the Q of lowest peak is a bit low. |
Line 41: | Line 64: |
* 作業 * PR2からの反射光が1m先で数cm下がっていた。10mradのオーダー。PR2が水平かどうかの確認。する予定。(苔山) * BS: ファーストコンタクトを今日剥がす(大石)。あとはブレッドボードの高さ調整と、リモートコントロールが必要。 |
* Work plan (*:responsible person) * Alignment and Vibration Isolation: *Izumi * We can move moving masses of BF, or IPs of yaw to check TF can be recovered. * We will play one more day under vacuum. * Type A: *Yokozawa * RT model of Type A will be separated into cryopayload and tower. * Type B * SR assembly continues. * Laser hazard: PSL. Green might be used late of the afternoon, then the center area and Y end will be the hazard area. |
Line 46: | Line 79: |
* 今週の目標はPR3からの光がBSまで届くこと。 * 問題点など * PR2の反射光を解決する必要がある。来週以降の遅れを生む可能性あり。 |
* Week of 2/5 * Finding causes of ETMY trouble. * Vent might be needed if ETMY is touching somewhere. * Cooling also will be delayed for 2weeks or so. * Issues * IP drifted 2mm in the air, and another 2mm when pump down. |
Line 54: | Line 92: |
<<Anchor(WeeklyMeetings)>> | |
Line 56: | Line 95: |
* Location: Meeting room at Hokum Kaikan, or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 66: | Line 118: |
* Meeting about SR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] |
Line 75: | Line 133: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/6(Tue.)
- Remote participants by eZuce: Takahashi
- Report of work (*:responsible person)
- Alignment and Vibration Isolation: Izumi, Okutomi
- BF yaw transfer function showed that it did not move well. It was fount that the position of IP was different from when pumping down started.
- IP drifted 2mm in the air, and another 2mm when pump down. (Takahashi)
- ETMY IPs were set back to where they were on 1/13. The transfer function now has the similar shape as before, but the Q of lowest peak is a bit low.
- Alignment and Vibration Isolation: Izumi, Okutomi
- Work plan (*:responsible person)
- Alignment and Vibration Isolation: *Izumi
- We can move moving masses of BF, or IPs of yaw to check TF can be recovered.
- We will play one more day under vacuum.
- Type A: *Yokozawa
- RT model of Type A will be separated into cryopayload and tower.
- Type B
- SR assembly continues.
- Alignment and Vibration Isolation: *Izumi
- Laser hazard: PSL. Green might be used late of the afternoon, then the center area and Y end will be the hazard area.
- Weekly
- Week of 2/5
- Finding causes of ETMY trouble.
- Vent might be needed if ETMY is touching somewhere.
- Cooling also will be delayed for 2weeks or so.
- Finding causes of ETMY trouble.
- Week of 2/5
- Issues
- IP drifted 2mm in the air, and another 2mm when pump down.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)