Differences between revisions 198 and 302 (spanning 104 versions)
Revision 198 as of 2017-12-12 09:18:35
Size: 7335
Comment:
Revision 302 as of 2018-02-19 09:08:05
Size: 8521
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/11 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}}
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
Line 20: Line 19:
 * ETMYアラインメント
  * 12/11
  * 12/12 和泉
  * 12/13 和泉
  * 12/14 和泉、長野、川﨑
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15

 * BS PDセット
  * 12/11
  * 12/12 横澤
  * 12/13 横澤
  * 12/14
  * 12/15
 * Beam leading to REFP port
  * *Izumi
Line 73: Line 54:
2017/12/12(Tue.) 2017/2/19(Mon.)
Line 75: Line 56:
 * Daily
  * 報告と作業 (*:責任者)
 * Remote participants by eZuce: None
  * Recovery from the power outage in the morning.
Line 78: Line 59:
   * アラインメント: *和泉、苔山、野替
    * 今日午後から、Xエンドのビームの確認、その後EYAに通す予定。PR2,3のOplevのダンピングをしたい。
    * 現在PR3は固定してあるが、Phase1の間は固定したままで残すことを考えている。
     * ワイヤーのテンションをきちんと張って落ち着かせる方法をVIRGOの人から聞いたので、とりあえずSRで試してみる予定。
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto
   * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
Glitch is still there but even if measurement with no glitch time has still no coherence.
Line 83: Line 64:
   * Type A: *高橋、奥富、宮本
    * Oplevのキャリブレーションについてklogに報告があった。どれだけ進んでいるのか要確認。
    * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。アルミホイルで塞ぐ方法もあるので、基本的に開ける方向で進める。
 * PR RT models will be modified for Watch dog bug or something.
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
Line 87: Line 67:
   * PD設置: 横澤
    * 明日PDをYendからBSに持ってくることになりそう。BSテーブルでのマウント方法を検討する必要がある。
 * Watch dog bug report: *Mark
  * Or stage was implemented instead of And stage at the watch dog part.
Line 90: Line 70:
   * Type B: *Mark、Enzo, 正田
    * 光学テーブルのアクチュエーターが一部働いていないところがあるのが見つかった。ハイパワーコイルドライバーでテストする。ドライバーが足りなくなって来ているので、SRでまだ使っていないものを持ってくる。
 * Work plan (*:responsible person)
  * CAL: *Haino
   * To check the safety of laser.
Line 93: Line 74:
  * ETMY: Enomomoto, Izumi
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.
Line 94: Line 78:

 
* Laser hazard
  * SRラインより奥。
 * Laser hazard: Upstream SR2-3 line.
Line 99: Line 81:
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
Line 100: Line 85:
  * 12/11の週
   * メインビームの再アラインメント。
   * ETMYからの戻り光確認。
   * 12/13 昼休みに真空引きの前のミーティング。
   * 12/18 EYC閉止。
  * Week of 2/26
   * Beam alignment to REFL port.
Line 106: Line 88:
  * week of 3/5
   * IYC door will be closed.
Line 107: Line 91:
 * 問題点など
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * BSテーブルにPDを置けるかどうか。
  * Eendの遮蔽板をいつ開けるか。
  * 真空引きの最終確認。
  * week of 3/12
   * Connecting ducts at corner.

 * Issues
Line 124: Line 107:
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
Line 131: Line 121:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 138: Line 128:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/19(Mon.)

  • Remote participants by eZuce: None
    • Recovery from the power outage in the morning.
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto
      • Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.

Glitch is still there but even if measurement with no glitch time has still no coherence.

  • PR RT models will be modified for Watch dog bug or something.
  • Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
  • Watch dog bug report: *Mark
    • Or stage was implemented instead of And stage at the watch dog part.
  • Work plan (*:responsible person)
    • CAL: *Haino
      • To check the safety of laser.
    • ETMY: Enomomoto, Izumi
      • Oplev will be centered and beam will be checked again.
      • PR2 will be lowered by ~3mm.
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Connecting ducts at corner.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)