Line 11: | Line 11: |
2017/12/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/11 * 12/12 和泉 * 12/13 和泉 * 12/14 和泉、長野、川﨑 * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/11 * 12/12 * 12/13 * 12/14 * 12/15 * BS PDセット * 12/11 * 12/12 横澤 * 12/13 横澤 * 12/14 * 12/15 |
* Beam leading to REFP port * *Izumi |
Line 73: | Line 54: |
2017/12/12(Tue.) | 2017/2/19(Mon.) |
Line 75: | Line 56: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by eZuce: None * Recovery from the power outage in the morning. |
Line 78: | Line 59: |
* アラインメント: *和泉、苔山、野替 * 今日午後から、Xエンドのビームの確認、その後EYAに通す予定。 * その際、PR2,3のOplevのダンピングをしたい。 * 現在PR3は固定してあるが、Phase1の間は固定したままで残すことを考えている。 * ワイヤーのテンションをきちんと張って落ち着かせる方法をVIRGOの人から聞いたので、とりあえずSRで試してみる予定。 |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned. Glitch is still there but even if measurement with no glitch time has still no coherence. |
Line 84: | Line 64: |
* Type A: *高橋、奥富、宮本 * Oplevのキャリブレーションについてklogに報告があった。どれだけ進んでいるのか要確認。 * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。アルミホイルで塞ぐ方法もあるので、基本的に開ける方向で進める。 |
* PR RT models will be modified for Watch dog bug or something. * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs. |
Line 88: | Line 67: |
* PD設置: 横澤 * 明日PDをYendからBSに持ってくることになりそう。BSテーブルでのマウント方法を検討する必要がある。 |
* Watch dog bug report: *Mark * Or stage was implemented instead of And stage at the watch dog part. |
Line 91: | Line 70: |
* Type B: *Mark、Enzo, 正田 * 光学テーブルのアクチュエーターが一部働いていないところがあるのが見つかった。ハイパワーコイルドライバーでテストする。ドライバーが足りなくなって来ているので、SRでまだ使っていないものを持ってくる。 |
* Work plan (*:responsible person) * CAL: *Haino * To check the safety of laser. |
Line 94: | Line 74: |
* ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. |
|
Line 95: | Line 78: |
* Laser hazard * SRラインより奥。 |
* Laser hazard: Upstream SR2-3 line. |
Line 100: | Line 81: |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
|
Line 101: | Line 85: |
* 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 |
* Week of 2/26 * Beam alignment to REFL port. |
Line 107: | Line 88: |
* week of 3/5 * IYC door will be closed. |
|
Line 108: | Line 91: |
* 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * BSテーブルにPDを置けるかどうか。 * Eendの遮蔽板をいつ開けるか。 * 真空引きの最終確認。 |
* week of 3/12 * Connecting ducts at corner. * Issues |
Line 125: | Line 107: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 132: | Line 121: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 139: | Line 128: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/19(Mon.)
- Remote participants by eZuce: None
- Recovery from the power outage in the morning.
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto
- Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
- Alignment and ETMY: *Izumi, Enomomoto
Glitch is still there but even if measurement with no glitch time has still no coherence.
- PR RT models will be modified for Watch dog bug or something.
- Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
- Watch dog bug report: *Mark
- Or stage was implemented instead of And stage at the watch dog part.
- Work plan (*:responsible person)
- CAL: *Haino
- To check the safety of laser.
- ETMY: Enomomoto, Izumi
- Oplev will be centered and beam will be checked again.
- PR2 will be lowered by ~3mm.
- CAL: *Haino
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Connecting ducts at corner.
- Week of 2/19
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)