Line 11: | Line 11: |
2017/12/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/13 和泉 * 12/14 和泉、長野、川﨑 * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/13 * 12/14 * 12/15 * BS PDセット * 12/13 横澤 * 12/14 * 12/15 |
* Beam leading to REFP port * *Izumi |
Line 67: | Line 54: |
2017/12/13(Wed.) | 2017/2/14(Wed.) |
Line 69: | Line 56: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by eZuce: None * Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work! |
Line 72: | Line 59: |
* アラインメント: *和泉 * YendのPDに光を届けた。BSを特にいじることなく、すぐに光が通った。PR2のダンピングを調整する必要があった。 * BSは依然10uradくらいのオーダーで揺れている。 * Type B: *Mark、Enzo, 正田, 和泉 * IP yaw, IM, TMのpitchのダンピングを入れた。 * Yawの動きがまだ大きい。これは全体の回転のようである。上のマグネティックダンパーで減衰されるはずがうまく効いていない。 * サスペンション全体が4mm程度下に下がっているかもしれない。 * 蓋を開けなければならないので、今日やることを考える。 * Type A: *牛場、宮本 * Yawが回転したが、力がある閾値を超えるとガクッと回るような感じである。ベアリングが渋い可能性が高い。 * 回るのも数分のオーダーで、微調整がかなり厳しそう。回転の方向は正しいことは確認した。 * BFのダンピングを強くするともう少し素直に反応する可能性がある。 * 今日は上部のダンピング制御を入れて操作して様子を見てみる。DC制御か? * PD設置: |
* Report of work (*:responsible person) * ETMY: *Enomomoto * Calibration at cryopayload was performed. * Cryo: mirror temperature: 220K. * Green reached ETMY * PR2 had 500urad misalignment. |
Line 92: | Line 68: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Returning IR light will be checked around BS. * Leveler wil be removed in the more |
|
Line 93: | Line 73: |
* Laser hazard * SRラインより奥。 * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。 |
* Green reached ETMY * PR2 had 500urad misalignment. * Laser hazard: IMM in the morning, SR2-3 in the afternoon. |
Line 98: | Line 80: |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * 2/16 Preparation for power down. |
|
Line 99: | Line 85: |
* 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
Line 105: | Line 89: |
* Week of 2/26 * Beam alignment to REFL port. |
|
Line 106: | Line 92: |
* 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * BSテーブルにPDを置けるかどうか。 * Eendの遮蔽板をいつ開けるか。 * 真空引きの最終確認。 |
* Issues * AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed. * DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know. |
Line 123: | Line 107: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 130: | Line 121: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 137: | Line 128: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/14(Wed.)
- Remote participants by eZuce: None
- Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work!
- Report of work (*:responsible person)
- ETMY: *Enomomoto
- Calibration at cryopayload was performed.
- Cryo: mirror temperature: 220K.
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: *Enomomoto
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Returning IR light will be checked around BS.
- Leveler wil be removed in the more
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: Enomomoto, Izumi
- Laser hazard: IMM in the morning, SR2-3 in the afternoon.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- 2/16 Preparation for power down.
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- Week of 2/13
- Issues
- AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed.
- DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools