Line 11: | Line 11: |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/14 和泉、長野、川﨑 * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/14 * 12/15 * BS PDセット * 12/14 横澤 * 12/15 * 遮蔽板取り外し * 木村 |
* Beam leading to REFP port * *Izumi |
Line 67: | Line 54: |
2017/12/14(Thu.) | 2017/2/16(Fri.) |
Line 69: | Line 56: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by eZuce: Yokozawa * Preparation of power outage at outside buildings on Sunday. * Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS. * Keep control room clean! |
Line 72: | Line 61: |
* 遮蔽板取り外し: *木村、その他 * 朝から取り外し作業開始。終了次第宮川まで連絡。 |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto * Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours. |
Line 75: | Line 65: |
* アラインメント: *和泉、長野、川崎、三代木 * ダンピング周りを見直している。PR3は0.2uradくらにまでなっている。 * 遮蔽板の取り外しが終わり次第アラインメント開始。 * ETMYのType A部分にモーターのスタックなどあるが、アラインメントには支障がなさそうなので、ETMYからの戻り光を確認するアラインメント作業は今日、明日で決行する。 |
* Green: *Michimura, Yokogawa, Sugimoto * Green hits ETMY and IR hits both ends. * Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen. |
Line 80: | Line 69: |
* Type B: *Mark、Enzo, 正田, 和泉 * 昨日言っていたキーストーンが4mm低いというのはLVDTのキャリブレーションの間違い。実際にはキーストンの位置を1.5mm上げた。 * それでもダンピングはまだ効いていないようである。 * IMのコントロールをアップデートした。多少改善したが、いまやっと10uradくらいの揺れになったくらい。 |
* Tcam: * Modifying some mechanical parts at KEK. |
Line 85: | Line 72: |
* Type A: *牛場、宮本 * Fishing rodの稼働実験をした。結果は残念ながら動かなかった。 * さらに作業中に、別件として新たにモーターが端まで行ってしまってstuckしてしまった。 * unstuckできるのが最速で月曜日。月曜のフタ締めの準備中にやるか? * この問題は垂直方向のことなので、アラインメント作業には直接は影響なさそう。 |
* Watch dog bug report: *Mark * Or stage was implemented instead of And stage at the watch dog part. |
Line 91: | Line 75: |
* PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next. | |
Line 92: | Line 77: |
* PD設置: * 和泉君の指示で移動のタイミングを横澤君に知らせる。 * 時期としては今日の午後か、明日の午前くらい。 |
* Work plan (*:responsible person) * CAL: *Haino * To check the safety of laser. |
Line 96: | Line 81: |
* ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. |
|
Line 97: | Line 85: |
* Laser hazard * SRラインより奥。 * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。 |
* Laser hazard: Upstream SR2-3 line. |
Line 103: | Line 88: |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * Green setup. * 2/16 Preparation for power down. |
|
Line 104: | Line 94: |
* 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
Line 110: | Line 98: |
* 12/18の週 * EYC閉止 |
* Week of 2/26 * Beam alignment to REFL port. |
Line 113: | Line 101: |
* week of 3/5 * IYC door will be closed. |
|
Line 114: | Line 104: |
* week of 3/12 * Vacuum at corner are will be performed in the week. |
|
Line 115: | Line 107: |
* 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * WSのアカウントを個別にしてほしい。(和泉、その他) -> LDAPを入れなければならず、結構大変(山本、宮川) |
* Issues |
Line 130: | Line 120: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 137: | Line 134: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 144: | Line 141: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/16(Fri.)
- Remote participants by eZuce: Yokozawa
- Preparation of power outage at outside buildings on Sunday.
- Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS.
- Keep control room clean!
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto
- Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours.
- Alignment and ETMY: *Izumi, Enomomoto
- Green: *Michimura, Yokogawa, Sugimoto
- Green hits ETMY and IR hits both ends.
- Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen.
- Tcam:
- Modifying some mechanical parts at KEK.
- Watch dog bug report: *Mark
- Or stage was implemented instead of And stage at the watch dog part.
- PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next.
- Work plan (*:responsible person)
- CAL: *Haino
- To check the safety of laser.
- ETMY: Enomomoto, Izumi
- Oplev will be centered and beam will be checked again.
- PR2 will be lowered by ~3mm.
- CAL: *Haino
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Green setup.
- 2/16 Preparation for power down.
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Vacuum at corner are will be performed in the week.
- Week of 2/13
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools