Line 11: | Line 11: |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/14 和泉、長野、川﨑 * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/14 * 12/15 * BS PDセット * 12/14 横澤 * 12/15 * 遮蔽板取り外し * 木村 |
* Beam leading to REFP port * *Izumi |
Line 67: | Line 54: |
2017/12/14(Thu.) | 2017/2/19(Mon.) |
Line 69: | Line 56: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by eZuce: None * Recovery from the power outage in the morning. |
Line 72: | Line 59: |
* 遮蔽板取り外し: *木村、その他 * 朝から取り外し作業開始。終了次第宮川まで連絡。 |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned. Glitch is still there but even if measurement with no glitch time has still no coherence. |
Line 75: | Line 64: |
* アラインメント: *和泉、長野、川崎、三代木 * ダンピング周りを見直している。PR3は0.2uradくらにまでなっている。 * 遮蔽板の取り外しが終わり次第アラインメント開始。 * ETMYのType A部分にモーターのスタックなどあるが、アラインメントには支障がなさそうなので、ETMYからの戻り光を確認するアラインメント作業は今日、明日で決行する。 |
* PR RT models will be modified for Watch dog bug or something. * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs. |
Line 80: | Line 67: |
* Type B: *Mark、Enzo, 正田, 和泉 * 昨日言っていたキーストーンが4mm低いというのはLVDTのキャリブレーションの間違い。実際にはキーストンの位置を1.5mm上げた。 * それでもダンピングはまだ効いていないようである。 * IMのコントロールをアップデートした。多少改善したが、いまやっと10uradくらいの揺れになったくらい。 |
* Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Damping tuning |
Line 85: | Line 71: |
* Type A: *牛場、宮本 * Fishing rodの稼働実験をした。結果は残念ながら動かなかった。 * さらに作業中に、別件として新たにモーターが端まで行ってしまってstuckしてしまった。 * unstuckできるのが最速で月曜日。月曜のフタ締めの準備中にやるか? * この問題は垂直方向のことなので、アラインメント作業には直接は影響なさそう。 * PD設置: * 和泉君の指示で移動のタイミングを横澤君に知らせる。 * 時期としては今日の午後か、明日の午前くらい。 * Laser hazard * SRラインより奥。 * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。 |
* Laser hazard: Upstream SR2-3 line. |
Line 103: | Line 74: |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
|
Line 104: | Line 78: |
* 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 |
* Week of 2/26 * Beam alignment to REFL port. |
Line 110: | Line 81: |
* 12/18の週 * EYC閉止 |
* week of 3/5 * IYC door will be closed. |
Line 113: | Line 84: |
* week of 3/12 * Connecting ducts at corner. |
|
Line 114: | Line 87: |
* 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * WSのアカウントを個別にしてほしい。(和泉、その他) -> LDAPを入れなければならず、結構大変(山本、宮川) |
* Issues * ETMY TF shows Q is getting lower and the resonant frequency is getting higher. Something is touching somewhere? |
Line 130: | Line 100: |
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 137: | Line 115: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 144: | Line 122: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/19(Mon.)
- Remote participants by eZuce: None
- Recovery from the power outage in the morning.
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto
- Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
- Alignment and ETMY: *Izumi, Enomomoto
Glitch is still there but even if measurement with no glitch time has still no coherence.
- PR RT models will be modified for Watch dog bug or something.
- Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Damping tuning
- ETMY: Enomomoto, Izumi
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Connecting ducts at corner.
- Week of 2/19
- Issues
- ETMY TF shows Q is getting lower and the resonant frequency is getting higher. Something is touching somewhere?
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools