2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 * BS PDセット * 12/15 横澤 |
* Beam leading to REFP port * *Izumi |
Line 62: | Line 54: |
2017/12/18(Mon.) | 2017/2/16(Fri.) |
Line 64: | Line 56: |
* Daily * 作業報告および作業予定 (*:責任者) * アラインメント: *和泉、長野、榎本、川崎 * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。 * BFのピコモーターが離散的に動く。5mrad程度のステップ。 * BFを固定した方がアラインメントはやりやすいのでは?(都丸) * アラインメントは今日はなし。 |
* Remote participants by eZuce: Yokozawa * Preparation of power outage at outside buildings on Sunday. * Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS. * Keep control room clean! |
Line 72: | Line 61: |
* Type A(ETMY): *牛場、宮本 * バネが動きを吸収している可能性があるので、バネを変える。 * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった? * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。 * 今日蓋閉めの準備のためにその作業をするので、 * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。 * 火曜日の夕方に方向性を判断。 |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto * Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours. |
Line 80: | Line 65: |
* PD設置: *横澤、和泉 * BSチェンバー内、AS側に設置完了。 * EYAにいってViewポートを取り付ける。 |
* Green: *Michimura, Yokogawa, Sugimoto * Green hits ETMY and IR hits both ends. * Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen. |
Line 84: | Line 69: |
* BSカメラ設置: *苔山、川崎 * BS付近に設置したが、レンズ交換が必要。 |
* Tcam: * Modifying some mechanical parts at KEK. |
Line 87: | Line 72: |
* Watch dog bug report: *Mark * Or stage was implemented instead of And stage at the watch dog part. |
|
Line 88: | Line 75: |
* Laser hazard * センターはSR奥がハザードエリア。エンドはハザードエリアなし。 |
* PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next. * Work plan (*:responsible person) * CAL: *Haino * To check the safety of laser. * ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. * Laser hazard: Upstream SR2-3 line. |
Line 92: | Line 88: |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * Green setup. * 2/16 Preparation for power down. |
|
Line 93: | Line 94: |
* 12/18の週 * EYC閉止 * Type A引き続き調整。 |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
Line 97: | Line 98: |
* Week of 2/26 * Beam alignment to REFL port. |
|
Line 98: | Line 101: |
* week of 3/5 * IYC door will be closed. |
|
Line 99: | Line 104: |
* 問題点など * 回路電源のモニターがあるといい。 |
* week of 3/12 * Vacuum at corner are will be performed in the week. * Issues |
Line 113: | Line 120: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 120: | Line 134: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 127: | Line 141: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/16(Fri.)
- Remote participants by eZuce: Yokozawa
- Preparation of power outage at outside buildings on Sunday.
- Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS.
- Keep control room clean!
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto
- Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours.
- Alignment and ETMY: *Izumi, Enomomoto
- Green: *Michimura, Yokogawa, Sugimoto
- Green hits ETMY and IR hits both ends.
- Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen.
- Tcam:
- Modifying some mechanical parts at KEK.
- Watch dog bug report: *Mark
- Or stage was implemented instead of And stage at the watch dog part.
- PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next.
- Work plan (*:responsible person)
- CAL: *Haino
- To check the safety of laser.
- ETMY: Enomomoto, Izumi
- Oplev will be centered and beam will be checked again.
- PR2 will be lowered by ~3mm.
- CAL: *Haino
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Green setup.
- 2/16 Preparation for power down.
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Vacuum at corner are will be performed in the week.
- Week of 2/13
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)