Line 11: Line 11:
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
Line 20: Line 19:
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑

 * BS PDセット
  * 12/15 横澤
 * Beam leading to REFP port
  * *Izumi
Line 62: Line 54:
2017/12/18(Mon.) 2017/2/19(Mon.)
Line 64: Line 56:
 * Daily
  * 作業報告および作業予定 (*:責任者)
   * アラインメント: *和泉、長野、榎本、川崎
    * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。
    * BFのピコモーターが離散的に動く。5mrad程度のステップ。
     * BFを固定した方がアラインメントはやりやすいのでは?(都丸)
    * アラインメントは今日はなし。
 * Remote participants by eZuce: None
  * Recovery from the power outage in the morning.
Line 72: Line 59:
   * Type A(ETMY): *牛場、宮本
    * バネが動きを吸収している可能性があるので、バネを変える。
    * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった?
    * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。
     * 今日蓋閉めの準備のためにその作業をするので、
    * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。
    * 火曜日の夕方に方向性を判断。
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto
   * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
Glitch is still there but even if measurement with no glitch time has still no coherence.
Line 80: Line 64:
   * PD設置: *横澤、和泉
    * BSチェンバー内、AS側に設置完了。
    * EYAにいってViewポートを取り付ける。
 * PR RT models will be modified for Watch dog bug or something.
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
Line 84: Line 67:
   * BSカメラ設置: *苔山、川崎
    * BS付近に設置したが、レンズ交換が必要。
 * Watch dog bug report: *Mark
  * Or stage was implemented instead of And stage at the watch dog part.
Line 87: Line 70:
 * Work plan (*:responsible person)
  * CAL: *Haino
   * To check the safety of laser.
Line 88: Line 74:
  * Laser hazard
   * センターはSR奥がハザードエリア。エンドはハザードエリアなし。
  * ETMY: Enomomoto, Izumi
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.

 * Laser hazard: Upstream SR2-3 line.
Line 92: Line 81:
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
Line 93: Line 85:
  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。
  * Week of 2/26
   * Beam alignment to REFL port.
Line 97: Line 88:
  * week of 3/5
   * IYC door will be closed.
Line 98: Line 91:
  * week of 3/12
   * Connecting ducts at corner.
Line 99: Line 94:
 * 問題点など
  * 回路電源のモニターがあるといい。
 * Issues
Line 113: Line 107:
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
Line 120: Line 121:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 127: Line 128:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/19(Mon.)

  • Remote participants by eZuce: None
    • Recovery from the power outage in the morning.
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto
      • Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.

Glitch is still there but even if measurement with no glitch time has still no coherence.

  • PR RT models will be modified for Watch dog bug or something.
  • Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
  • Watch dog bug report: *Mark
    • Or stage was implemented instead of And stage at the watch dog part.
  • Work plan (*:responsible person)
    • CAL: *Haino
      • To check the safety of laser.
    • ETMY: Enomomoto, Izumi
      • Oplev will be centered and beam will be checked again.
      • PR2 will be lowered by ~3mm.
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Connecting ducts at corner.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1