Line 11: | Line 11: |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 * BS PDセット * 12/15 横澤 |
* Beam leading to REFP port * *Izumi |
Line 62: | Line 54: |
2017/12/19(Tue.) | 2017/2/21(Wed.) |
Line 64: | Line 56: |
* 作業報告 (*:責任者) * Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本 * BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。 * Fishing rodのスタックも直した。 |
* Remote participants by eZuce: None |
Line 69: | Line 58: |
* Vierport: *横澤、井上 * EYAにViewport設置完了。 |
* Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * We moved IP position to find where it does not touch anywhere, but TF showed resonant frequency was higher. We think heat link make some torque. |
Line 72: | Line 62: |
* IMMTが動かない件 * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。 * コイルドライバーがおかしい可能性がある。 * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。 * アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。 |
* BS: Kozu * Finished measurement the TF of TM and IM coupling. |
Line 78: | Line 65: |
* 作業予定 (*:責任者) * アラインメント: *和泉 * 今日の昼休み12時から1時の間にスリットを置く。 |
* Team: *Inoue * Team at Yend was broken. Taking too many pictures was one of the reasons. |
Line 82: | Line 68: |
* Type A(ETMY): *高橋、牛場、都丸、和泉 * Fishing rodが動くか確認。 * IOO * ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。 * MCの調子が悪い。 |
* ISS: Koseyama, and Toyama Univ. * Error signal is limited by shot noise, but outlook noise is still higher. |
Line 90: | Line 72: |
* Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. |
|
Line 91: | Line 76: |
* Laser hazard * センターはSR奥がハザードエリア。 * 午後からYend 1Fがハザートエリアになる。 |
* Team: * Debugging NIKON camera. * IYA monitor: Yokozawa * IYA monitor will start. * ISS: Koseyama, and Toyama Univ. * Investigating noise. * Laser hazard: Upstream SR2-3 line. |
Line 96: | Line 89: |
* Week of 2/19 * ETMY tuninng. |
|
Line 97: | Line 92: |
* 12/18の週 * EYC閉止 * Type A引き続き調整。 * ETMYのアラインメント |
* Week of 2/26 * Beam alignment to REFL port. |
Line 102: | Line 95: |
* week of 3/5 * IYC door will be closed. |
|
Line 103: | Line 98: |
* 問題点など * 回路電源のモニターがあるといい。 * MCの調子が悪い。 * IMMTが動かない件 * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。 * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。 |
* week of 3/12 * Connecting ducts at corner. |
Line 110: | Line 101: |
* Issues * Heat link make some torque. |
|
Line 121: | Line 114: |
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 129: | Line 129: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 136: | Line 136: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/19 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/21(Wed.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- We moved IP position to find where it does not touch anywhere, but TF showed resonant frequency was higher. We think heat link make some torque.
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- BS: Kozu
- Finished measurement the TF of TM and IM coupling.
- Team: *Inoue
- Team at Yend was broken. Taking too many pictures was one of the reasons.
- ISS: Koseyama, and Toyama Univ.
- Error signal is limited by shot noise, but outlook noise is still higher.
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Diagonalizing matrix to close loop of marionette.
- Team:
- Debugging NIKON camera.
- IYA monitor: Yokozawa
- IYA monitor will start.
- ISS: Koseyama, and Toyama Univ.
- Investigating noise.
- ETMY: Enomomoto, Izumi
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Connecting ducts at corner.
- Week of 2/19
- Issues
- Heat link make some torque.
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)