Differences between revisions 219 and 312 (spanning 93 versions)
Revision 219 as of 2017-12-20 09:22:01
Size: 7858
Comment:
Revision 312 as of 2018-02-23 09:13:00
Size: 9143
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
Line 20: Line 19:
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑

 * BS PDセット
  * 12/15 横澤
 * Beam leading to REFP port
  * *Izumi
Line 62: Line 54:
2017/12/20(Wed.) 2017/2/23(Fri.)
Line 64: Line 56:
 * 作業報告 (*:責任者)
  * Alignment of ETMY: *和泉、牛場、佐藤、都丸、高橋
   * BSからETMYはpitchに10uradくらいのズレがあったが、Oplevを見て戻すと特に問題なく光はエンドに当たった。
   * スリットを使う(三代木法)ことで、BS側に戻すのも相当順調だった。実際にスリットを外してすぐにBSのPDが反応した。
   * ETMYのPayloadのYawに200uradくらいの揺れが残っている。ヒートリンクに触ってしまった可能性が高い。ダンピングが必要。
    * Pitchも数十urad位揺れている。Pitchはおそらく上からのエアーで揺れている可能性が高い。
   * 光はYendで14000カウントでていたが、BSで6000カウントになった。予測とほぼ一致している。
 * Remote participants by eZuce: None
Line 72: Line 58:
  * IMMTが動かない件
   * IMMT2のYawのピコモーターが一方向には動くが、逆方向には動きにくい。手でネジを回すと一旦直る。すでに2-3度起きているので、再現性がありそう。
   * DACカードの順序が入れ替わっているようである。->DGS
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 76: Line 63:
  * IOO: 苔山、古畑、坂本、北澤
   * ISSのアラインメントがほぼ完了。AOMを触らなければならない時点でストップした。
   * MCのBURTがきちんと戻っていなかって、MCのサーボのゲインが間違っていたのでMCが不安定だった。直したら、安定になった。(和泉)
  * ETMY Camera is still under debugging. Camera seems to be broken.
  * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa
   * working for guardian.
Line 80: Line 68:
 * 作業予定 (*:責任者)
  * Alignment of ETMY: *和泉、高橋、牛場、都丸、宮本
   * Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。
Line 84: Line 69:
  * IOO
   * アラインメントがあるので、今日の作業は他のことをする。
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.
Line 87: Line 73:
  * BS: Oplevの位置の初期化をしたい。   * ISS: Koseyama, Kitazawa
   * Making RT models.
Line 89: Line 76:
 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。

 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
Line 94: Line 80:
  * Week of 2/19
   * ETMY tuninng.
Line 95: Line 83:
  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。
  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
Line 100: Line 87:
 * Week of 12/25
  * 停電の可能性あり。
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
Line 104: Line 100:
 * 問題点など
 * Issues
   * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 117: Line 114:
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 125: Line 129:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 132: Line 136:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/19 updated KAGRA/Commissioning/Commissioning_schedule_20180220.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/23(Fri.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
      • Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
      • It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
    • ETMY Camera is still under debugging. Camera seems to be broken.
    • ITMY camera was aligned, and needs focus next.
    • IOO: Kitazawa
      • working for guardian.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Izumi
      • Diagonalizing matrix to close loop of marionette.
    • ISS: Koseyama, Kitazawa
      • Making RT models.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
  • Weekly
    • Week of 2/19
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
      • 2/28: Height change for PRs
    • week of 3/5
      • IYC door will be closed.
      • Exchanging items and cleaning inside the PR2 chamber
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
  • Issues
    • The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
    • DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)