Line 11: | Line 11: |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 * BS PDセット * 12/15 横澤 |
* Beam leading to REFP port * *Izumi |
Line 62: | Line 54: |
2017/12/21(Thu.) | 2017/2/13(Tue.) |
Line 64: | Line 56: |
* Report of work (*:責任者) * Alignment of ETMY: *Ushiba, Sato, Takahashi R, Miyamoto, Tomaru, Yokozawa * Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。 |
* Remote participants by eZuce: None * Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work! |
Line 68: | Line 59: |
* BS: Oplevの位置の初期化をしたい。 * Work plan (*:責任者) |
* Report of work (*:responsible person) * ETMY: *Enomomoto * Calibration at cryopayload was performed. * Cryo: mirror temperature: 220K. * Green reached ETMY * PR2 had 500urad misalignment. |
Line 73: | Line 67: |
* Laser hazard * センターはSR奥がハザードエリア。 * 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。 |
* Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Returning IR light will be checked around BS. * Leveler wil be removed in the more * Green reached ETMY * PR2 had 500urad misalignment. * Laser hazard: IMM in the morning, SR2-3 in the afternoon. |
Line 78: | Line 80: |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. |
|
Line 79: | Line 84: |
* Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 |
* Week of 2/19 * ETMY tuninng. |
Line 84: | Line 87: |
* Week of 12/25 * Planed power outage in the afternoon on 12/15. |
* Week of 2/26 * Beam alignment to REFL port. * Issues * AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed. * DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know. |
Line 88: | Line 95: |
* Issues * k1imcでDACの入れ替えが起こっている |
|
Line 101: | Line 106: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 109: | Line 120: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 116: | Line 127: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/13(Tue.)
- Remote participants by eZuce: None
- Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work!
- Report of work (*:responsible person)
- ETMY: *Enomomoto
- Calibration at cryopayload was performed.
- Cryo: mirror temperature: 220K.
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: *Enomomoto
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Returning IR light will be checked around BS.
- Leveler wil be removed in the more
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: Enomomoto, Izumi
- Laser hazard: IMM in the morning, SR2-3 in the afternoon.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- Week of 2/13
- Issues
- AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed.
- DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)