Line 11: | Line 11: |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 * Green setting on PR2: * 12/26 *Akutsu, Yokogawa + 1 or 2 * 12/27 *Yokogawa + 1 or 2 |
* *: responsible person * Beam leading to REFP port * *Izumi |
Line 54: | Line 54: |
2017/12/22(Fri.) | 2017/2/15(Thur.) * Remote participants by eZuce: None |
Line 57: | Line 59: |
* Alignment of ETMY: *Ushiba, Sato, Takahashi R, Miyamoto, Tomaru, Yokozawa * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。 |
* ETMY: *Enomomoto * IP damping was established. Loop of LVDT to LVDT including DC works well. * Optimum of point IP can be moved. Needs check again. * Alignment: *Izumi * Beam pointing to ETMY and BS was confirmed. * ETMY oplev moved more than 180urad, the reasons is not clear. * Somebody could hit the table of optical table. * Spot of ETMY by Tcam showed oplev spot moved a little. * Spot of "3" shape seems to be a reflection of something close. * Green: *Michimura, Yokogawa, Sugimoto * Green has been aligned to ETMY. * Beam is hitting at PR2 with 10cm off from center. * WAB: * Akutsu, Miyo, Simon * Making Photo sensors. One of the sensor was connected to ADC. * Door will be closed in the week of 3/5. * Sensors will be left after cooling. |
Line 61: | Line 82: |
* 停電のために真空層の蓋を閉める。(内山) | * CAL: *Inoue, Yokozawa, Haino * IYA will be opened to complete Tcam. |
Line 63: | Line 85: |
* ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. |
|
Line 64: | Line 89: |
* Laser hazard * センターはSR奥がハザードエリア。 |
* Laser hazard: SR2-3. |
Line 68: | Line 92: |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * Green setup. * 2/16 Preparation for power down. |
|
Line 69: | Line 98: |
* Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
Line 74: | Line 102: |
* Week of 12/25 * Planed power outage in the afternoon on 12/25. |
* Week of 2/26 * Beam alignment to REFL port. |
Line 77: | Line 105: |
* week of 3/5 * IYC door will be closed. |
|
Line 79: | Line 109: |
* k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい | |
Line 91: | Line 121: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 99: | Line 135: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 106: | Line 142: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/15(Thur.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- ETMY: *Enomomoto
- IP damping was established. Loop of LVDT to LVDT including DC works well.
- Optimum of point IP can be moved. Needs check again.
- ETMY: *Enomomoto
- Alignment: *Izumi
- Beam pointing to ETMY and BS was confirmed.
- ETMY oplev moved more than 180urad, the reasons is not clear.
- Somebody could hit the table of optical table.
- Spot of ETMY by Tcam showed oplev spot moved a little.
- Spot of "3" shape seems to be a reflection of something close.
- ETMY oplev moved more than 180urad, the reasons is not clear.
- Beam pointing to ETMY and BS was confirmed.
- Green: *Michimura, Yokogawa, Sugimoto
- Green has been aligned to ETMY.
- Beam is hitting at PR2 with 10cm off from center.
- WAB: * Akutsu, Miyo, Simon
- Making Photo sensors. One of the sensor was connected to ADC.
- Door will be closed in the week of 3/5.
- Sensors will be left after cooling.
- Green has been aligned to ETMY.
- Work plan (*:responsible person)
- CAL: *Inoue, Yokozawa, Haino
- IYA will be opened to complete Tcam.
- ETMY: Enomomoto, Izumi
- Oplev will be centered and beam will be checked again.
- PR2 will be lowered by ~3mm.
- CAL: *Inoue, Yokozawa, Haino
- Laser hazard: SR2-3.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Green setup.
- 2/16 Preparation for power down.
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- Week of 2/13
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)