Differences between revisions 223 and 313 (spanning 90 versions)
Revision 223 as of 2017-12-22 09:06:29
Size: 6335
Comment:
Revision 313 as of 2018-02-23 09:16:23
Size: 9215
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
Line 17: Line 17:
* 責任者
  * Green setting on PR2:
   * 12/26 *Akutsu, Yokogawa + 1 or 2
   * 12/27 *Yokogawa + 1 or 2
 * *: responsible person

 * Beam leading to REFP port
  * *Izumi
Line 54: Line 54:
2017/12/22(Fri.) 2017/2/23(Fri.)

 * Remote participants by eZuce: None
Line 57: Line 59:
  * Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa
   * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.

  * Camera: Inoue, Haino, Yokozawa, Cory, Binhua
   * ETMY Camera is still under debugging. Camera seems to be broken.
   * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa, kokeyama
   * Making guardian script for ISS.
Line 61: Line 71:
  * 停電のために真空層の蓋を閉める。(内山)   * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.

  * ISS: Koseyama, Kitazawa
   * Making RT models.
Line 64: Line 78:
 * Laser hazard
   * センターはSR奥がハザードエリア。
 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
Line 68: Line 81:
  * Week of 2/19
   * ETMY tuninng.
Line 69: Line 84:
  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。
  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
Line 74: Line 88:
 * Week of 12/25
  * Planed power outage in the afternoon on 12/25.
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber

  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
Line 79: Line 102:
  * k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい    * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 91: Line 115:
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 99: Line 130:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 106: Line 137:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/19 updated KAGRA/Commissioning/Commissioning_schedule_20180220.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/23(Fri.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
      • Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
      • It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
    • Camera: Inoue, Haino, Yokozawa, Cory, Binhua
      • ETMY Camera is still under debugging. Camera seems to be broken.
      • ITMY camera was aligned, and needs focus next.
    • IOO: Kitazawa, kokeyama
      • Making guardian script for ISS.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Izumi
      • Diagonalizing matrix to close loop of marionette.
    • ISS: Koseyama, Kitazawa
      • Making RT models.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
  • Weekly
    • Week of 2/19
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
      • 2/28: Height change for PRs
    • week of 3/5
      • IYC door will be closed.
      • Exchanging items and cleaning inside the PR2 chamber
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
  • Issues
    • The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
    • DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)