Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person

 * Beam leading to REFP port
  * *Izumi
Line 51: Line 54:
2017/1/5(Fri.) 2017/2/16(Fri.)
Line 53: Line 56:
 * Remote participants by educe: None

 * 停電からの復帰関連
  * DGS: PR3も復帰した。DACが一枚不調だった。k1imcのDACを一枚抜いた。入れ替えは直っているはず。
  * IOO: MCまで復帰。回路も特に問題ない。
  * Type A: Remoteで測定した模様。
  * 真空: MC再起動。腕はまだ(来週)。
  * Tcam: 2秒間隔で見えるようになった。
 * Remote participants by eZuce: Yokozawa
  * Preparation of power outage at outside buildings on Sunday.
  * Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS.
  * Keep control room clean!
Line 64: Line 62:
  * Alignment and ETMY: *Izumi, Enomomoto
   * Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours.
Line 65: Line 65:
  * AOS: *Akutsu
   * PR2の横にグリーンを構築しつつある。
    * 今日はビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。
 * Green: *Michimura, Yokogawa, Sugimoto
  * Green hits ETMY and IR hits both ends.
  * Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen.
Line 71: Line 69:
 * Tcam:
  * Modifying some mechanical parts at KEK.

 * Watch dog bug report: *Mark
  * Or stage was implemented instead of And stage at the watch dog part.

 * PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next.
Line 73: Line 78:
  * AOS: *Akutsu, yokokawa, yoshioka, kokeyama
   * グリーンのビームプロファイルなど。
   * EYのマリオネット作業の可能性あり。
  * IOO: *Kokeyama, others
   * ISS準備と実験。
  * CAL: *Haino
   * To check the safety of laser.
Line 79: Line 81:
  * ETMY: Enomomoto, Izumi
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.
Line 80: Line 85:
 * Laser hazard
   * センターはIFI奥がハザードエリア。IR/Green用メガネを着用のこと。
 * Laser hazard: Upstream SR2-3 line.
Line 84: Line 88:
  * Week of 1/5   * Week of 2/13
   * Waiting for cooling the mirror.
   * ETMY tuninng.
   * Green setup.
   * 2/16 Preparation for power down.
Line 86: Line 94:
  * Week of 1/8
   * meeting
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
Line 91: Line 98:
  * Week of 1/15
   * Pump down, leak check in the later of this week.
  * Week of 2/26
   * Beam alignment to REFL port.

  * week of 3/5
   * IYC door will be closed.

  * week of 3/12
   * Vacuum at corner are will be performed in the week.
Line 95: Line 108:
  * Remoteでの接続が遅い。VPNかk1gateのDNSか?
Line 108: Line 120:
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 116: Line 134:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 123: Line 141:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/16(Fri.)

  • Remote participants by eZuce: Yokozawa
    • Preparation of power outage at outside buildings on Sunday.
    • Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS.
    • Keep control room clean!
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto
      • Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours.
  • Green: *Michimura, Yokogawa, Sugimoto
    • Green hits ETMY and IR hits both ends.
    • Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen.
  • Tcam:
    • Modifying some mechanical parts at KEK.
  • Watch dog bug report: *Mark
    • Or stage was implemented instead of And stage at the watch dog part.
  • PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next.
  • Work plan (*:responsible person)
    • CAL: *Haino
      • To check the safety of laser.
    • ETMY: Enomomoto, Izumi
      • Oplev will be centered and beam will be checked again.
      • PR2 will be lowered by ~3mm.
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/13
      • Waiting for cooling the mirror.
      • ETMY tuninng.
      • Green setup.
      • 2/16 Preparation for power down.
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Vacuum at corner are will be performed in the week.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members