Differences between revisions 226 and 302 (spanning 76 versions)
Revision 226 as of 2018-01-05 09:10:50
Size: 6873
Comment:
Revision 302 as of 2018-02-19 09:08:05
Size: 8521
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person

 * Beam leading to REFP port
  * *Izumi
Line 51: Line 54:
2017/1/5(Fri.) 2017/2/19(Mon.)
Line 53: Line 56:
 * Remote participants by educe: None

 * 停電からの復帰関連
  * DGS: PR3も復帰した。DACが一枚不調だった。k1imcのDACを一枚抜いた。入れ替えは直っているはず。
  * IOO: MCまで復帰。回路も特に問題ない。
  * Type A: Remoteで測定した模様。
  * 真空: MC再起動。腕はまだ(来週)。
  * Tcam: 2秒間隔で見えるようになった。
 * Remote participants by eZuce: None
  * Recovery from the power outage in the morning.
Line 64: Line 60:
  * Alignment and ETMY: *Izumi, Enomomoto
   * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
Glitch is still there but even if measurement with no glitch time has still no coherence.
Line 65: Line 64:
  * AOS: *Akutsu
   * PR2の横にグリーンを構築しつつある。
    * 今日はビームプロファイルなど。
   * EYのマリオネットにOplevを取り付ける、関連が部品などの不具合があり進んでいない。
    * 今日は引き続き作業の可能性あり。
 * PR RT models will be modified for Watch dog bug or something.
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
Line 71: Line 67:
 * Watch dog bug report: *Mark
  * Or stage was implemented instead of And stage at the watch dog part.
Line 73: Line 71:
  * AOS: *Akutsu, yokokawa, yoshioka, kokeyama
   * グリーンのビームプロファイルなど。
   * EYのマリオネット作業の可能性あり。
  * IOO: *Kokeyama, others
   * ISS準備と実験。
  * CAL: *Haino
   * To check the safety of laser.
Line 79: Line 74:
  * ETMY: Enomomoto, Izumi
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.
Line 80: Line 78:
 * Laser hazard
   * センターはIFI奥がハザードエリア。IR/Green用メガネを着用のこと。
 * Laser hazard: Upstream SR2-3 line.
Line 84: Line 81:
  * Week of 1/5   * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
Line 86: Line 85:
  * Week of 1/8
   * meeting
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.
  * Week of 2/26
   * Beam alignment to REFL port.
Line 91: Line 88:
  * Week of 1/15
   * Pump down, leak check in the later of this week.
  * week of 3/5
   * IYC door will be closed.

  * week of 3/12
   * Connecting ducts at corner.
Line 95: Line 95:
  * Remoteでの接続が遅い。VPNかk1gateのDNSか?
Line 108: Line 107:
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 116: Line 121:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 123: Line 128:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/19(Mon.)

  • Remote participants by eZuce: None
    • Recovery from the power outage in the morning.
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto
      • Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.

Glitch is still there but even if measurement with no glitch time has still no coherence.

  • PR RT models will be modified for Watch dog bug or something.
  • Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
  • Watch dog bug report: *Mark
    • Or stage was implemented instead of And stage at the watch dog part.
  • Work plan (*:responsible person)
    • CAL: *Haino
      • To check the safety of laser.
    • ETMY: Enomomoto, Izumi
      • Oplev will be centered and beam will be checked again.
      • PR2 will be lowered by ~3mm.
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Connecting ducts at corner.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)