Differences between revisions 230 and 308 (spanning 78 versions)
Revision 230 as of 2018-01-05 13:36:42
Size: 6546
Comment:
Revision 308 as of 2018-02-21 09:14:35
Size: 8718
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person

 * Beam leading to REFP port
  * *Izumi
Line 51: Line 54:
2017/1/5(Fri.) 2017/2/21(Wed.)
Line 53: Line 56:
 * Remote participants by educe: None  * Remote participants by eZuce: None
Line 55: Line 58:
 * 停電からの復帰関連
  * DGS: PR3も復帰した。DACが一枚不調だった。k1imcのDACを一枚抜いた。入れ替えは直っているはず。
  * IOO: MCまで復帰。回路も特に問題ない。
  * 真空: MC再起動。腕はまだ(来週)。
  * Tcam: 2秒間隔で見えるようになった。
 * Report of work (*:responsible person)
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * We moved IP position to find where it does not touch anywhere, but TF showed resonant frequency was higher. We think heat link make some torque.

 * BS: Kozu
  * Finished measurement the TF of TM and IM coupling.

 * Team: *Inoue
  * Team at Yend was broken. Taking too many pictures was one of the reasons.

 * ISS: Koseyama, and Toyama Univ.
  * Error signal is limited by shot noise, but outlook noise is still higher.
Line 62: Line 72:
 * Report of work (*:responsible person)
  * Type A: Remoteで測定していた模様。
 * Work plan (*:responsible person)
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.
Line 65: Line 76:
 * Work plan (*:responsible person)   * Team:
   * Debugging NIKON camera.

  * IYA monitor: Yokozawa
   * IYA monitor will start.

  * ISS: Koseyama, and Toyama Univ.
   * Investigating noise.
Line 68: Line 86:
 * Laser hazard
  * センターはIMM奥がハザードエリア。
 * Laser hazard: Upstream SR2-3 line.
Line 72: Line 89:
  * Week of 1/5   * Week of 2/19
   * ETMY tuninng.
Line 74: Line 92:
  * Week of 1/8
   * meeting
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.
  * Week of 2/26
   * Beam alignment to REFL port.
Line 79: Line 95:
  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.
  * week of 3/5
   * IYC door will be closed.

  * week of 3/12
   * Connecting ducts at corner.
Line 84: Line 102:
  * Remoteでの接続が遅い。VPNかk1gateのDNSか?
  * Heat link make some torque.
Line 97: Line 114:
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
Line 106: Line 129:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 113: Line 136:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/19 updated KAGRA/Commissioning/Commissioning_schedule_20180220.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/21(Wed.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
      • We moved IP position to find where it does not touch anywhere, but TF showed resonant frequency was higher. We think heat link make some torque.
  • BS: Kozu
    • Finished measurement the TF of TM and IM coupling.
  • Team: *Inoue
    • Team at Yend was broken. Taking too many pictures was one of the reasons.
  • ISS: Koseyama, and Toyama Univ.
    • Error signal is limited by shot noise, but outlook noise is still higher.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Izumi
      • Diagonalizing matrix to close loop of marionette.
    • Team:
      • Debugging NIKON camera.
    • IYA monitor: Yokozawa
      • IYA monitor will start.
    • ISS: Koseyama, and Toyama Univ.
      • Investigating noise.
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/19
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Connecting ducts at corner.
  • Issues
    • Heat link make some torque.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)