Comment:
|
8840
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180109.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Beam leading to REFP port * *Izumi |
Line 51: | Line 54: |
2017/1/9(Tue.) | 2017/2/15(Thur.) |
Line 53: | Line 56: |
* Remote participants by educe: Izumi, Yokozawa, Miyoki | * Remote participants by eZuce: None |
Line 56: | Line 59: |
* IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。 * Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。 * Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。 |
* ETMY: *Enomomoto * IP damping was established. Loop of LVDT to LVDT including DC works well. * Optimum of point IP can be moved. Needs check again. * Alignment: *Izumi * Beam pointing to ETMY and BS was confirmed. * ETMY oplev moved more than 180urad, the reasons is not clear. * Somebody could hit the table of optical table. * Spot of ETMY by Tcam showed oplev spot moved a little. * Spot of "3" shape seems to be a reflection of something close. * Green: *Michimura, Yokogawa, Sugimoto * Green has been aligned to ETMY. * Beam is hitting at PR2 with 10cm off from center. * WAB: * Akutsu, Miyo, Simon * Making Photo sensors. One of the sensor was connected to ADC. * Door will be closed in the week of 3/5. * Sensors will be left after cooling. |
Line 61: | Line 82: |
* CAL: *Inoue, Yokozawa, Haino * IYA will be opened to complete Tcam. |
|
Line 62: | Line 85: |
* Cryo: Yendの外回りの配線チェック。 * 光てこの話と、真空中のPDの検討をする必要がある。 |
* ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. |
Line 65: | Line 89: |
* Laser hazard * センターはIMM奥がハザードエリア。 |
* Laser hazard: SR2-3. |
Line 70: | Line 92: |
* Week of 1/8 * vacuum meeting 12:30 on 1/10, at fan hut. * Re-alignment for IFO on 1/11, 12. * Damping for ETMY on 1/13, 14. |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * Green setup. * 2/16 Preparation for power down. |
Line 75: | Line 98: |
* Week of 1/15 * IOO works. * Pump down, leak check in the later of this week. |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. * Week of 2/26 * Beam alignment to REFL port. * week of 3/5 * IYC door will be closed. |
Line 92: | Line 121: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || |
|
Line 101: | Line 135: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 108: | Line 142: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/15(Thur.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- ETMY: *Enomomoto
- IP damping was established. Loop of LVDT to LVDT including DC works well.
- Optimum of point IP can be moved. Needs check again.
- ETMY: *Enomomoto
- Alignment: *Izumi
- Beam pointing to ETMY and BS was confirmed.
- ETMY oplev moved more than 180urad, the reasons is not clear.
- Somebody could hit the table of optical table.
- Spot of ETMY by Tcam showed oplev spot moved a little.
- Spot of "3" shape seems to be a reflection of something close.
- ETMY oplev moved more than 180urad, the reasons is not clear.
- Beam pointing to ETMY and BS was confirmed.
- Green: *Michimura, Yokogawa, Sugimoto
- Green has been aligned to ETMY.
- Beam is hitting at PR2 with 10cm off from center.
- WAB: * Akutsu, Miyo, Simon
- Making Photo sensors. One of the sensor was connected to ADC.
- Door will be closed in the week of 3/5.
- Sensors will be left after cooling.
- Green has been aligned to ETMY.
- Work plan (*:responsible person)
- CAL: *Inoue, Yokozawa, Haino
- IYA will be opened to complete Tcam.
- ETMY: Enomomoto, Izumi
- Oplev will be centered and beam will be checked again.
- PR2 will be lowered by ~3mm.
- CAL: *Inoue, Yokozawa, Haino
- Laser hazard: SR2-3.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Green setup.
- 2/16 Preparation for power down.
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- Week of 2/13
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools