Line 11: | Line 11: |
2017/1/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180109.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Beam leading to REFP port * *Izumi |
Line 51: | Line 54: |
2017/1/9(Tue.) | 2017/2/16(Fri.) |
Line 53: | Line 56: |
* Remote participants by educe: Izumi, Yokozawa, Miyoki | * Remote participants by eZuce: Yokozawa * Preparation of power outage at outside buildings on Sunday. * Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS. * Keep control room clean! |
Line 56: | Line 62: |
* IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。 * Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。 * Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。 |
* Alignment and ETMY: *Izumi, Enomomoto * Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours. * Green: *Michimura, Yokogawa, Sugimoto * Green hits ETMY and IR hits both ends. * Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen. * Tcam: * Modifying some mechanical parts at KEK. * Watch dog bug report: *Mark * Or stage was implemented instead of And stage at the watch dog part. * PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next. |
Line 61: | Line 78: |
* CAL: *Haino * To check the safety of laser. |
|
Line 62: | Line 81: |
* Cryo: Yendの外回りの配線チェック。 * 光てこの話と、真空中のPDの検討をする必要がある。 |
* ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. |
Line 65: | Line 85: |
* Laser hazard * センターはIMM奥がハザードエリア。 |
* Laser hazard: Upstream SR2-3 line. |
Line 70: | Line 88: |
* Week of 1/8 * vacuum meeting 12:30 on 1/10, at fan hut. * Re-alignment for IFO on 1/11, 12. * Damping for ETMY on 1/13, 14. |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * Green setup. * 2/16 Preparation for power down. |
Line 75: | Line 94: |
* Week of 1/15 * IOO works. * Pump down, leak check in the later of this week. |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. * Week of 2/26 * Beam alignment to REFL port. * week of 3/5 * IYC door will be closed. * week of 3/12 * Vacuum at corner are will be performed in the week. |
Line 92: | Line 120: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || |
|
Line 101: | Line 134: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 108: | Line 141: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/16(Fri.)
- Remote participants by eZuce: Yokozawa
- Preparation of power outage at outside buildings on Sunday.
- Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS.
- Keep control room clean!
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto
- Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours.
- Alignment and ETMY: *Izumi, Enomomoto
- Green: *Michimura, Yokogawa, Sugimoto
- Green hits ETMY and IR hits both ends.
- Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen.
- Tcam:
- Modifying some mechanical parts at KEK.
- Watch dog bug report: *Mark
- Or stage was implemented instead of And stage at the watch dog part.
- PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next.
- Work plan (*:responsible person)
- CAL: *Haino
- To check the safety of laser.
- ETMY: Enomomoto, Izumi
- Oplev will be centered and beam will be checked again.
- PR2 will be lowered by ~3mm.
- CAL: *Haino
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Green setup.
- 2/16 Preparation for power down.
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Vacuum at corner are will be performed in the week.
- Week of 2/13
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)