Line 11: Line 11:
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/12 *Izumi
Line 21: Line 19:
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
 * Beam leading to REFP port
  * *Izumi
Line 60: Line 54:
2017/1/12(Fri.) 2017/2/23(Fri.)
Line 62: Line 56:
 * Remote participants by educe: None

 * Affect of short power failure
  * VIS
   * EX のポラリティーが反転していた。瞬停と関係あるかは不明。

  * IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
   * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.

  * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.
 * Remote participants by eZuce: None
Line 74: Line 59:
  * Alignment: *Izumi
   * X-armまでリカバーした。
   * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
    * GASは真空槽を開けずに直せる範囲を超えている模様。
    * PR3で100uradのオーダーでずれていた。
    * Oplevの範囲をすでに超えてしまっている。
  * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
   * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
   * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 81: Line 63:

  * PLC at Yend: Aso
   * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。

  * Marionet Oplev: Akutsu
   * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
  * Camera: Inoue, Haino, Yokozawa, Cory, Binhua
   * ETMY Camera is still under debugging. Camera seems to be broken.
   * ITMY camera was aligned, and needs focus next.
  * IOO: Kitazawa, kokeyama
   * Making guardian script for ISS.
Line 90: Line 71:
  * Alignment: *Izumi
   * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。
  * ETMY: Enomomoto, Izumi
   * Diagonalizing matrix to close loop of marionette.
Line 93: Line 74:
  * Marionet Oplev: Akutsu
   * QPDの信号を確認する予定。
  * ISS: Koseyama, Kitazawa
   * Making RT models.
Line 96: Line 77:
 
 * Laser hazard area
  * Behind of BS and
SR line and Yend 1F

 * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
Line 101: Line 81:
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.
  * Week of 2/19
   * ETMY tuninng.
Line 105: Line 84:
  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.
  * Week of 2/26
   * Beam alignment to REFL port.
   * 2/28: Height change for PRs
Line 109: Line 88:
  * Week of 1/22
   * 1/24,25 leak check.
  * week of 3/5
   * IYC door will be closed.
   * Exchanging items and cleaning inside the PR2 chamber
Line 112: Line 92:
  * Week of 1/29
   * 1/29 Cooling start
  * week of 3/12
   * TMS installation at ETMY.
   * Connecting ducts at the corner area.

  * week of 3/19
   * Vacuum test at at the corner area.
   * TMS alignment using green light at ETMY.
Line 116: Line 102:
   * EX のポラリティーが反転していた。回路の問題か?
   * 真空曹を開けてPR2とPR3を直すかどうか。
   * The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
   * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
Line 129: Line 115:
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
Line 139: Line 130:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 146: Line 137:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])  * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/19 updated KAGRA/Commissioning/Commissioning_schedule_20180220.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/23(Fri.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
      • Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
      • It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
    • Camera: Inoue, Haino, Yokozawa, Cory, Binhua
      • ETMY Camera is still under debugging. Camera seems to be broken.
      • ITMY camera was aligned, and needs focus next.
    • IOO: Kitazawa, kokeyama
      • Making guardian script for ISS.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Izumi
      • Diagonalizing matrix to close loop of marionette.
    • ISS: Koseyama, Kitazawa
      • Making RT models.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
  • Weekly
    • Week of 2/19
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
      • 2/28: Height change for PRs
    • week of 3/5
      • IYC door will be closed.
      • Exchanging items and cleaning inside the PR2 chamber
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
  • Issues
    • The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
    • DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools