2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/12(Fri.) | 2017/2/14(Wed.) |
Line 62: | Line 56: |
* Remote participants by educe: None * Affect of short power failure * VIS * EX のポラリティーが反転していた。瞬停と関係あるかは不明。 * IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC. * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now. |
* Remote participants by eZuce: None * Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work! |
Line 74: | Line 60: |
* Alignment: *Izumi * X-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。 * GASは真空槽を開けずに直せる範囲を超えている模様。 * PR3で100uradのオーダーでずれていた。 * Oplevの範囲をすでに超えてしまっている。 |
* ETMY: *Enomomoto * Calibration at cryopayload was performed. * Cryo: mirror temperature: 220K. * Green reached ETMY * PR2 had 500urad misalignment. |
Line 81: | Line 66: |
* PLC at Yend: Aso * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。 * Marionet Oplev: Akutsu * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。 |
|
Line 90: | Line 69: |
* Alignment: *Izumi * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。 |
* ETMY: Enomomoto, Izumi * Returning IR light will be checked around BS. * Leveler wil be removed in the more |
Line 93: | Line 73: |
* Marionet Oplev: Akutsu * QPDの信号を確認する予定。 |
* Green reached ETMY * PR2 had 500urad misalignment. |
Line 96: | Line 76: |
* Laser hazard area * Behind of BS and SR line and Yend 1F |
* Laser hazard: IMM in the morning, SR2-3 in the afternoon. |
Line 101: | Line 80: |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * 2/16 Preparation for power down. |
Line 105: | Line 85: |
* Week of 1/15 * IOO works. * 1/19: Pump down. |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
Line 109: | Line 89: |
* Week of 1/22 * 1/24,25 leak check. * Week of 1/29 * 1/29 Cooling start |
* Week of 2/26 * Beam alignment to REFL port. |
Line 116: | Line 93: |
* EX のポラリティーが反転していた。回路の問題か? * 真空曹を開けてPR2とPR3を直すかどうか。 |
* AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed. * DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know. |
Line 129: | Line 107: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 139: | Line 121: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 146: | Line 128: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/14(Wed.)
- Remote participants by eZuce: None
- Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work!
- Report of work (*:responsible person)
- ETMY: *Enomomoto
- Calibration at cryopayload was performed.
- Cryo: mirror temperature: 220K.
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: *Enomomoto
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Returning IR light will be checked around BS.
- Leveler wil be removed in the more
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: Enomomoto, Izumi
- Laser hazard: IMM in the morning, SR2-3 in the afternoon.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- 2/16 Preparation for power down.
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- Week of 2/13
- Issues
- AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed.
- DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools