Line 11: | Line 11: |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/15(Mon.) | 2017/2/21(Wed.) |
Line 62: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: None |
Line 65: | Line 59: |
* Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo * ETMYのダンピングとBSのL2P。ETMYは100urad程度だったのが、10uradくらいになった。あと一桁欲しい。 * BSのLを押してPが出ないようにする。DCはうまくいったが高周波がまだ十分でない。 * 干渉計ビームはX-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが数mmのオーダーで上に上がってピッチが変わったが、角度でいうと10uradくらいのオーダーでずれるだけなのでOK, ただビームスポットはcmのオーダーでずれる。直すのは延期。 |
* Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * We moved IP position to find where it does not touch anywhere, but TF showed resonant frequency was higher. We think heat link make some torque. |
Line 71: | Line 62: |
* 温度が一旦下がってから一度くらい上がった。問題なければ今のを保つ。 | * BS: Kozu * Finished measurement the TF of TM and IM coupling. |
Line 73: | Line 65: |
* Team: *Inoue * Team at Yend was broken. Taking too many pictures was one of the reasons. |
|
Line 74: | Line 68: |
* Marionet Oplev: Akutsu * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。 |
* ISS: Koseyama, and Toyama Univ. * Error signal is limited by shot noise, but outlook noise is still higher. |
Line 79: | Line 73: |
* Alignment: *Izumi * Buffule PDを入れるので、その回路を用意する。 |
* ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. |
Line 82: | Line 76: |
* 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。 | * Team: * Debugging NIKON camera. |
Line 84: | Line 79: |
* PLC at Yend: Aso * MEDMを作成している。 * Laser hazard area * Behind of BS and SR line and Yend 1F |
* IYA monitor: Yokozawa * IYA monitor will start. * ISS: Koseyama, and Toyama Univ. * Investigating noise. * Laser hazard: Upstream SR2-3 line. |
Line 91: | Line 89: |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. |
* Week of 2/19 * ETMY tuninng. |
Line 95: | Line 92: |
* Week of 1/15 * IOO works. * 1/19: Pump down. |
* Week of 2/26 * Beam alignment to REFL port. |
Line 99: | Line 95: |
* Week of 1/22 * 1/24,25 leak check. |
* week of 3/5 * IYC door will be closed. |
Line 102: | Line 98: |
* Week of 1/29 * 1/29 Cooling start * Laser hazard: to be changed to IMM line in the morning. |
* week of 3/12 * Connecting ducts at corner. |
Line 108: | Line 102: |
* Heat link make some torque. | |
Line 119: | Line 114: |
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 129: | Line 129: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 136: | Line 136: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/19 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/21(Wed.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- We moved IP position to find where it does not touch anywhere, but TF showed resonant frequency was higher. We think heat link make some torque.
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- BS: Kozu
- Finished measurement the TF of TM and IM coupling.
- Team: *Inoue
- Team at Yend was broken. Taking too many pictures was one of the reasons.
- ISS: Koseyama, and Toyama Univ.
- Error signal is limited by shot noise, but outlook noise is still higher.
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Diagonalizing matrix to close loop of marionette.
- Team:
- Debugging NIKON camera.
- IYA monitor: Yokozawa
- IYA monitor will start.
- ISS: Koseyama, and Toyama Univ.
- Investigating noise.
- ETMY: Enomomoto, Izumi
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Connecting ducts at corner.
- Week of 2/19
- Issues
- Heat link make some torque.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)