Line 11: | Line 11: |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/15(Mon.) | 2017/2/22(Thur.) |
Line 62: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: Miyoki |
Line 65: | Line 59: |
* Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo * ETMYのダンピングとBSのL2P。ETMYは100urad程度だったのが、10uradくらいになった。あと一桁欲しい。 * BSのLを押してPが出ないようにする。DCはうまくいったが高周波がまだ十分でない。 * 干渉計ビームはX-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが数mmのオーダーで上に上がってピッチが変わったが、角度でいうと10uradくらいのオーダーでずれるだけなのでOK, ただビームスポットはcmのオーダーでずれる。直すのは延期。 |
* Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Diagonalizing input matrix. Electronics was something wrong, like oscillation. |
Line 71: | Line 62: |
* 温度が一旦下がってから一度くらい上がった。問題なければ今のを保つ。 | * BS: Kozu * Finished measurement the TF of TM and IM coupling. * ISS: Koseyama, Sakamoto. * Measuring TF. * Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. * ISS: Koseyama, Kitazawa * Making RT models. |
Line 74: | Line 76: |
* Marionet Oplev: Akutsu * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。 * Work plan (*:responsible person) * Alignment: *Izumi * Buffule PDを入れるので、その回路を用意する。 * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。 * PLC at Yend: Aso * MEDMを作成している。 * Laser hazard area * Behind of BS and SR line and Yend 1F |
* Laser hazard: AM: PSL, PM: Upstream SR2-3 line. |
Line 91: | Line 79: |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. |
* Week of 2/19 * ETMY tuninng. |
Line 95: | Line 82: |
* Week of 1/15 * IOO works. * 1/19: Pump down. |
* Week of 2/26 * Beam alignment to REFL port. * Height change for PRs |
Line 99: | Line 86: |
* Week of 1/22 * 1/24,25 leak check. |
* week of 3/5 * IYC door will be closed. |
Line 102: | Line 89: |
* Week of 1/29 * 1/29 Cooling start |
* week of 3/12 * Exchanging items and cleaning inside the PR2 chamber * Connecting ducts at the corner area. |
Line 105: | Line 93: |
* Laser hazard: to be changed to IMM line in the morning. | * week of 3/19 * Vacuum test at at the corner area. |
Line 119: | Line 109: |
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 129: | Line 124: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 136: | Line 131: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/19 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/22(Thur.)
- Remote participants by eZuce: Miyoki
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- Diagonalizing input matrix. Electronics was something wrong, like oscillation.
- BS: Kozu
- Finished measurement the TF of TM and IM coupling.
- ISS: Koseyama, Sakamoto.
- Measuring TF.
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Diagonalizing matrix to close loop of marionette.
- ISS: Koseyama, Kitazawa
- Making RT models.
- ETMY: Enomomoto, Izumi
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- Height change for PRs
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Exchanging items and cleaning inside the PR2 chamber
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- Week of 2/19
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools