Line 11: | Line 11: |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/15(Mon.) | 2017/2/23(Fri.) |
Line 62: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: None |
Line 65: | Line 59: |
* Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo * ETMYのダンピングとBSのL2P。ETMYは100urad程度だったのが、10uradくらいになった。あと一桁欲しい。 * BSのLを押してPが出ないようにするフィルターを実装している。DCはうまくいったが高周波がまだ十分でない。 * 先週の時点で干渉計ビームはX-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが数mmのオーダーで上に上がってピッチが変わったが、角度でいうと10uradくらいのオーダーでずれるだけなのでOK, ただビームスポットはcmのオーダーでずれる。PR系を直すのは来週以降に延期。 |
* Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified. * It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
Line 71: | Line 63: |
* 温度が一旦下がってから一度くらい上がった。問題なければ今のを保つ。 | * ETMY Camera is still under debugging. Camera seems to be broken. * ITMY camera was aligned, and needs focus next. * IOO: Kitazawa * working for guardian. |
Line 74: | Line 70: |
* Alignment: *Izumi * Baffle PDを入れるので、その回路を用意する。 |
* ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. |
Line 77: | Line 73: |
* PLC at Yend: Aso * MEDMを作成している。 * Laser hazard: to be changed to IMM line in the morning. |
* ISS: Koseyama, Kitazawa * Making RT models. * Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end. |
Line 83: | Line 80: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. |
* Week of 2/19 * ETMY tuninng. |
Line 89: | Line 83: |
* Week of 1/22 * 1/24,25 leak check. |
* Week of 2/26 * Beam alignment to REFL port. * 2/28: Height change for PRs |
Line 92: | Line 87: |
* Week of 1/29 * 1/29 Cooling start |
* week of 3/5 * IYC door will be closed. * Exchanging items and cleaning inside the PR2 chamber * week of 3/12 * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. |
Line 97: | Line 101: |
* The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified. * DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced. |
|
Line 108: | Line 114: |
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 118: | Line 129: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 125: | Line 136: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/19 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/23(Fri.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- Photo sensors was investigated and it was turned out that the satellite amplifier has an oscillation above 10kHz. Capacitors were added, then the oscillation went away. All the satellite amplifier should be modified.
- It was turned out that the glitch at the ETMY comes from DAC. DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
- ETMY Camera is still under debugging. Camera seems to be broken.
- ITMY camera was aligned, and needs focus next.
- IOO: Kitazawa
- working for guardian.
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Diagonalizing matrix to close loop of marionette.
- ISS: Koseyama, Kitazawa
- Making RT models.
- ETMY: Enomomoto, Izumi
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
- Weekly
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- 2/28: Height change for PRs
- week of 3/5
- IYC door will be closed.
- Exchanging items and cleaning inside the PR2 chamber
- week of 3/12
- TMS installation at ETMY.
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- TMS alignment using green light at ETMY.
- Week of 2/19
- Issues
- The satellite amplifier has an oscillation above 10kHz. All the satellite amplifier should be modified.
- DAC output has sometimes zero voltage for 100ms~1s. IO chassis will be replaced.
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)