7218
Comment:
|
8518
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/16 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/16(Tue.) | 2017/2/22(Thur.) |
Line 62: | Line 56: |
* Remote participants by educe: Inoue | * Remote participants by eZuce: Miyoki |
Line 65: | Line 59: |
* Alignment: *Izumi * Baffle PDを入れるので、その回路を用意している。Oplev回路を改造してつかう。 |
* Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Diagonalizing input matrix. Electronics was something wrong, like oscillation. |
Line 68: | Line 62: |
* BS: 新井 * L2Pをフィルターを設計した。DCもそこそ、高周波もかなりいったが、すごく低い周波数はもう少し改良する必要がある。 |
* BS: Kozu * Finished measurement the TF of TM and IM coupling. * ISS: Koseyama, Sakamoto. * Measuring TF. |
Line 72: | Line 69: |
* Alignment: *Izumi * EYでものの準備など。 |
* ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. |
Line 75: | Line 72: |
* Laser hazard: Upstream of IMM line. | * ISS: Koseyama, Kitazawa * Making RT models. * Laser hazard: AM: PSL, PM: Upstream SR2-3 line. |
Line 79: | Line 79: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. |
* Week of 2/19 * ETMY tuninng. |
Line 85: | Line 82: |
* Week of 1/22 * 1/24,25 leak check. |
* Week of 2/26 * Beam alignment to REFL port. * Height change for PRs |
Line 88: | Line 86: |
* Week of 1/29 * 1/29 Cooling start |
* week of 3/5 * IYC door will be closed. * week of 3/12 * Exchanging items and cleaning inside the PR2 chamber * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. |
Line 104: | Line 109: |
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 114: | Line 124: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 121: | Line 131: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/19 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/22(Thur.)
- Remote participants by eZuce: Miyoki
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- Diagonalizing input matrix. Electronics was something wrong, like oscillation.
- BS: Kozu
- Finished measurement the TF of TM and IM coupling.
- ISS: Koseyama, Sakamoto.
- Measuring TF.
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Diagonalizing matrix to close loop of marionette.
- ISS: Koseyama, Kitazawa
- Making RT models.
- ETMY: Enomomoto, Izumi
- Laser hazard: AM: PSL, PM: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- Height change for PRs
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Exchanging items and cleaning inside the PR2 chamber
- Connecting ducts at the corner area.
- week of 3/19
- Vacuum test at at the corner area.
- Week of 2/19
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools