8229
Comment:
|
8101
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/16 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/2/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/18(Thur.) | 2017/2/9(Fri.) |
Line 62: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: None |
Line 65: | Line 59: |
* Alignment: *Izumi * EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。 * ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。 * CryoPayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。 |
* Alignment and Vibration Isolation: *Miyakawa * Drift by cooling is small. |
Line 70: | Line 62: |
* IOO * PSL上のパワーを変更して、メインパワーを1Wまで上げた。実際には干渉計直前で蹴っているので、干渉計側には今まで通り100mW程度が入っている。メインパワーの変動が数十%と大きくなってしまっている。今の所変動の原因は不明。 |
* Cooling: *Kimura, Suzuki, Yokozawa, Aso, Miyakawa, Miyamoto * One of the cooled was stopped due to the leak of water. This will be fixed in the next week. It does not affect the schedule of cooling. (Kimura) * PLC values are fixed. Power cable on the wall once accidentally might be unplugged and plugged, then PC was not turned on. (Aso) * Some of the temperature channels have been fixed. (Miyakawa, Miyamoto, Yokozawa) |
Line 75: | Line 68: |
* Alignment: *Izumi * BSからETMYにビームを飛ばしたが、まだ見えていない。ゲインが500倍くらい低かったせい。午後3、4時頃から、再度ゲインを上げて試す。 * CryoPayloadのVisual inspection. * φ800フランジは今日は開けておく。明日しめる。 |
|
Line 80: | Line 69: |
* IOO * 1WをMCに入れる * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment. |
* Laser hazard: PSL room in the morning. IMM in the afternoon. |
Line 86: | Line 72: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. * Week of 1/29 * 1/29 Cooling start |
* Week of 2/5 * 2/7 Cooling. |
Line 100: | Line 77: |
* Network cableの整理 | |
Line 112: | Line 89: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 122: | Line 103: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 129: | Line 110: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/9(Fri.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment and Vibration Isolation: *Miyakawa
- Drift by cooling is small.
- Cooling: *Kimura, Suzuki, Yokozawa, Aso, Miyakawa, Miyamoto
- One of the cooled was stopped due to the leak of water. This will be fixed in the next week. It does not affect the schedule of cooling. (Kimura)
- PLC values are fixed. Power cable on the wall once accidentally might be unplugged and plugged, then PC was not turned on. (Aso)
- Some of the temperature channels have been fixed. (Miyakawa, Miyamoto, Yokozawa)
- Alignment and Vibration Isolation: *Miyakawa
- Work plan (*:responsible person)
- Laser hazard: PSL room in the morning. IMM in the afternoon.
- Weekly
- Week of 2/5
- 2/7 Cooling.
- Week of 2/5
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools