8570
Comment:
|
8718
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/18 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/2/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/19(Thur.) | 2017/2/21(Wed.) |
Line 62: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: None |
Line 65: | Line 59: |
* Vacuum * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY. |
* Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * We moved IP position to find where it does not touch anywhere, but TF showed resonant frequency was higher. We think heat link make some torque. |
Line 68: | Line 62: |
* IOO: *Kokeyama * 1WがMCに入った。 |
* BS: Kozu * Finished measurement the TF of TM and IM coupling. |
Line 71: | Line 65: |
* Alignment: *Izumi * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。 * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。 * ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。 |
* Team: *Inoue * Team at Yend was broken. Taking too many pictures was one of the reasons. * ISS: Koseyama, and Toyama Univ. * Error signal is limited by shot noise, but outlook noise is still higher. |
Line 77: | Line 73: |
* Alignment: *Izumi * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。 * 11時頃からレーザーハザードを全域に変更してアラインメント作業。 |
* ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. * Team: * Debugging NIKON camera. * IYA monitor: Yokozawa * IYA monitor will start. * ISS: Koseyama, and Toyama Univ. * Investigating noise. |
Line 82: | Line 86: |
* 真空引きの最終判断は月曜日にする。 * チェックリスト最終確認。 * φ800フランジを閉める。 * Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM. |
* Laser hazard: Upstream SR2-3 line. |
Line 90: | Line 89: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting |
* Week of 2/19 * ETMY tuninng. |
Line 95: | Line 92: |
* Week of 1/22 * 1/23: Pump down. * 1/24: Turbo pump on. |
* Week of 2/26 * Beam alignment to REFL port. |
Line 99: | Line 95: |
* Week of 1/29 * 1/29,30 leak check. * 1/31? Cooling start. |
* week of 3/5 * IYC door will be closed. |
Line 103: | Line 98: |
* week of 3/12 * Connecting ducts at corner. |
|
Line 105: | Line 102: |
* Network cableの整理 | * Heat link make some torque. |
Line 117: | Line 114: |
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || |
|
Line 128: | Line 129: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/19 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/21(Wed.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- We moved IP position to find where it does not touch anywhere, but TF showed resonant frequency was higher. We think heat link make some torque.
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- BS: Kozu
- Finished measurement the TF of TM and IM coupling.
- Team: *Inoue
- Team at Yend was broken. Taking too many pictures was one of the reasons.
- ISS: Koseyama, and Toyama Univ.
- Error signal is limited by shot noise, but outlook noise is still higher.
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Diagonalizing matrix to close loop of marionette.
- Team:
- Debugging NIKON camera.
- IYA monitor: Yokozawa
- IYA monitor will start.
- ISS: Koseyama, and Toyama Univ.
- Investigating noise.
- ETMY: Enomomoto, Izumi
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Connecting ducts at corner.
- Week of 2/19
- Issues
- Heat link make some torque.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools