Line 11: Line 11:
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
Line 18: Line 18:

 * Pump down
  * 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 57: Line 54:
2017/1/19(Thur.) 2017/2/19(Mon.)
Line 59: Line 56:
 * Remote participants by educe: None  * Remote participants by eZuce: None
  * Recovery from the power outage in the morning.
Line 62: Line 60:
  * Vacuum
   * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
  * Alignment and ETMY: *Izumi, Enomomoto
   * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
Glitch is still there but even if measurement with no glitch time has still no coherence.
Line 65: Line 64:
  * IOO: *Kokeyama
   * 1WがMCに入った。

  * Alignment: *Izumi
   * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
   * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
   * ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。
 * PR RT models will be modified for Watch dog bug or something.
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
Line 74: Line 68:
  * Alignment: *Izumi
   * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
   * 11時頃からレーザーハザードを全域に変更してアラインメント作業。
  * ETMY: Enomomoto, Izumi
   * Damping tuning
Line 78: Line 71:

  * 真空引きの最終判断は月曜日にする。
   * チェックリスト最終確認。
   * φ800フランジを閉める。

 
 * Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM.
 * Laser hazard: Upstream SR2-3 line.
Line 87: Line 74:
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
Line 92: Line 78:
  * Week of 1/22
   * 1/23: Pump down.
   * 1/24: Turbo pump on.
  * Week of 2/26
   * Beam alignment to REFL port.
Line 96: Line 81:
  * Week of 1/29
   * 1/29,30 leak check.
  * week of 3/5
   * IYC door will be closed.
Line 99: Line 84:
  * Week of 2/5

   * Cooling start.
  * week of 3/12
   * Connecting ducts at corner.
Line 105: Line 88:
  * Network cableの整理   * ETMY TF shows Q is getting lower and the resonant frequency is getting higher. Something is touching somewhere?
Line 117: Line 100:
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
Line 128: Line 114:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/19(Mon.)

  • Remote participants by eZuce: None
    • Recovery from the power outage in the morning.
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto
      • Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.

Glitch is still there but even if measurement with no glitch time has still no coherence.

  • PR RT models will be modified for Watch dog bug or something.
  • Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Izumi
      • Damping tuning
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Connecting ducts at corner.
  • Issues
    • ETMY TF shows Q is getting lower and the resonant frequency is getting higher. Something is touching somewhere?

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)