Line 11: Line 11:
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
2017/2/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}}
Line 18: Line 18:

 * Pump down
  * 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 57: Line 54:
2017/1/23(Tue.) 2017/2/15(Thur.)
Line 59: Line 56:
 * Remote participants by educe: Aso  * Remote participants by eZuce: None
Line 62: Line 59:
  * None   * ETMY: *Enomomoto
   * IP damping was established. Loop of LVDT to LVDT including DC works well.
   * Optimum of point IP can be moved. Needs check again.

 * Alignment: *Izumi
  * Beam pointing to ETMY and BS was confirmed.
   * ETMY oplev moved more than 180urad, the reasons is not clear.
    * Somebody could hit the table of optical table.
    * Spot of ETMY by Tcam showed oplev spot moved a little.
   * Spot of "3" shape seems to be a reflection of something close.

 * Green: *Michimura, Yokogawa, Sugimoto
  * Green has been aligned to ETMY.
   * Beam is hitting at PR2 with 10cm off from center.

  * WAB: * Akutsu, Miyo, Simon
   * Making Photo sensors. One of the sensor was connected to ADC.
   * Door will be closed in the week of 3/5.
   * Sensors will be left after cooling.

Line 65: Line 82:
  * Vacuum
   * 本日午後真空引き予定
    * ETMY立会い: 木村、鈴木、都丸、横澤、高橋(センター)、阿久津(センター)、宮川
    * コントロールルーム: 和泉、奥富
   * φ800フランジ締め
   * dial gaugeセット
   * Oplev確認
   * Tcam確認
   * Check listによる最終確認
  * CAL: *Inoue, Yokozawa, Haino
   * IYA will be opened to complete Tcam.
Line 75: Line 85:
 * IOO: 苔山
  * 午後にTilt sensorやPMCなどの作業あり。
  * ETMY: Enomomoto, Izumi
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.
Line 78: Line 89:
  * Alignment: *Izumi
   * BS modelのテコ入れ: Izumi

 * Laser hazard: 今日は午前はPSL、午後からIMM、夕方から夜間にかけて全域。
 * Laser hazard: SR2-3.
Line 84: Line 92:
  * Week of 1/22
   * 1/23: Pump down.
   * 1/24: Turbo pump on.
  * Week of 2/13
   * Waiting for cooling the mirror.
   * ETMY tuninng.
   * Green setup.
   * 2/16 Preparation for power down.
Line 88: Line 98:
  * Week of 1/29
   * 1/29,30 leak check.
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
Line 91: Line 102:
  * Week of 2/5
   * 2/5 Cooling start.
  * Week of 2/26
   * Beam alignment to REFL port.
Line 94: Line 105:
  * week of 3/5
   * IYC door will be closed.
Line 96: Line 109:
  * Network cableの整理
Line 108: Line 121:
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/12 updated KAGRA/Commissioning/Commissioning_schedule_20180213.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/15(Thur.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • ETMY: *Enomomoto
      • IP damping was established. Loop of LVDT to LVDT including DC works well.
      • Optimum of point IP can be moved. Needs check again.
  • Alignment: *Izumi
    • Beam pointing to ETMY and BS was confirmed.
      • ETMY oplev moved more than 180urad, the reasons is not clear.
        • Somebody could hit the table of optical table.
        • Spot of ETMY by Tcam showed oplev spot moved a little.
      • Spot of "3" shape seems to be a reflection of something close.
  • Green: *Michimura, Yokogawa, Sugimoto
    • Green has been aligned to ETMY.
      • Beam is hitting at PR2 with 10cm off from center.
    • WAB: * Akutsu, Miyo, Simon
      • Making Photo sensors. One of the sensor was connected to ADC.
      • Door will be closed in the week of 3/5.
      • Sensors will be left after cooling.
  • Work plan (*:responsible person)
    • CAL: *Inoue, Yokozawa, Haino
      • IYA will be opened to complete Tcam.
    • ETMY: Enomomoto, Izumi
      • Oplev will be centered and beam will be checked again.
      • PR2 will be lowered by ~3mm.
  • Laser hazard: SR2-3.
  • Weekly
    • Week of 2/13
      • Waiting for cooling the mirror.
      • ETMY tuninng.
      • Green setup.
      • 2/16 Preparation for power down.
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)