2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 18: | Line 18: |
* Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
|
Line 57: | Line 54: |
2017/1/26(Fri.) | 2017/2/14(Wed.) |
Line 59: | Line 56: |
* Remote participants by eZuce: | * Remote participants by eZuce: None * Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work! |
Line 62: | Line 60: |
* ETMY: *Enomomoto * Calibration at cryopayload was performed. * Cryo: mirror temperature: 220K. * Green reached ETMY * PR2 had 500urad misalignment. |
|
Line 63: | Line 66: |
* Vacuum * ターボポンプを入れた。 |
|
Line 66: | Line 67: |
* Alignment * Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。 * AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada * k1iy0への電源ケーブルの仕上げ。 * IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。 |
|
Line 74: | Line 69: |
* 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。 * Alignment: Oplevのセンタリング。 |
* ETMY: Enomomoto, Izumi * Returning IR light will be checked around BS. * Leveler wil be removed in the more * Green reached ETMY * PR2 had 500urad misalignment. |
Line 78: | Line 77: |
* Laser hazard: Upstream of IMMT line | * Laser hazard: IMM in the morning, SR2-3 in the afternoon. |
Line 81: | Line 80: |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. |
Line 85: | Line 84: |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. |
* Week of 2/19 * ETMY tuninng. |
Line 89: | Line 87: |
* Week of 2/5 * 2/5 Cooling start. |
* Week of 2/26 * Beam alignment to REFL port. * Issues * AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed. * DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know. |
Line 93: | Line 95: |
* Issues * Network cableの整理 * ピコモーターの反応がなくなる。 |
|
Line 107: | Line 106: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/14(Wed.)
- Remote participants by eZuce: None
- Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work!
- Report of work (*:responsible person)
- ETMY: *Enomomoto
- Calibration at cryopayload was performed.
- Cryo: mirror temperature: 220K.
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: *Enomomoto
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Returning IR light will be checked around BS.
- Leveler wil be removed in the more
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: Enomomoto, Izumi
- Laser hazard: IMM in the morning, SR2-3 in the afternoon.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- Week of 2/13
- Issues
- AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed.
- DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know.
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)