Line 11: | Line 11: |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 18: | Line 18: |
* Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
|
Line 57: | Line 54: |
2017/1/26(Fri.) | 2017/2/16(Fri.) |
Line 59: | Line 56: |
* Remote participants by eZuce: | * Remote participants by eZuce: Yokozawa * Preparation of power outage at outside buildings on Sunday. * Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS. * Keep control room clean! |
Line 62: | Line 62: |
* Alignment and ETMY: *Izumi, Enomomoto * Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours. |
|
Line 63: | Line 65: |
* Vacuum * ターボポンプを入れた。 |
* Green: *Michimura, Yokogawa, Sugimoto * Green hits ETMY and IR hits both ends. * Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen. |
Line 66: | Line 69: |
* Alignment * Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。 * AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada * k1iy0への電源ケーブルの仕上げ。 * IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。 |
* Tcam: * Modifying some mechanical parts at KEK. * Watch dog bug report: *Mark * Or stage was implemented instead of And stage at the watch dog part. * PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next. |
Line 74: | Line 78: |
* 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。 * Alignment: Oplevのセンタリング。 |
* CAL: *Haino * To check the safety of laser. |
Line 77: | Line 81: |
* ETMY: Enomomoto, Izumi * Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. |
|
Line 78: | Line 85: |
* Laser hazard: Upstream of IMMT line | * Laser hazard: Upstream SR2-3 line. |
Line 81: | Line 88: |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. * Green setup. * 2/16 Preparation for power down. |
Line 85: | Line 94: |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. |
* Week of 2/19 * 2/19 Recovering for power down. * ETMY tuninng. |
Line 89: | Line 98: |
* Week of 2/5 * 2/5 Cooling start. |
* Week of 2/26 * Beam alignment to REFL port. |
Line 92: | Line 101: |
* week of 3/5 * IYC door will be closed. * week of 3/12 * Vacuum at corner are will be performed in the week. |
|
Line 94: | Line 108: |
* Network cableの整理 * ピコモーターの反応がなくなる。 |
|
Line 107: | Line 120: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/16(Fri.)
- Remote participants by eZuce: Yokozawa
- Preparation of power outage at outside buildings on Sunday.
- Please prepare for shutdown your items, specially release DC output to prevent kicking for VIS.
- Keep control room clean!
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto
- Scripts to measure 32 DOFs of ETMY have been implemented and measured last night for 7hours.
- Alignment and ETMY: *Izumi, Enomomoto
- Green: *Michimura, Yokogawa, Sugimoto
- Green hits ETMY and IR hits both ends.
- Beam spot seen in the morning of yesterday was a bounced light. Now direct beam is being seen.
- Tcam:
- Modifying some mechanical parts at KEK.
- Watch dog bug report: *Mark
- Or stage was implemented instead of And stage at the watch dog part.
- PR2: Lower stage was failed. Range was too small. Using the fishing rods will be tried next.
- Work plan (*:responsible person)
- CAL: *Haino
- To check the safety of laser.
- ETMY: Enomomoto, Izumi
- Oplev will be centered and beam will be checked again.
- PR2 will be lowered by ~3mm.
- CAL: *Haino
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Green setup.
- 2/16 Preparation for power down.
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Vacuum at corner are will be performed in the week.
- Week of 2/13
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)