Differences between revisions 270 and 305 (spanning 35 versions)
Revision 270 as of 2018-01-26 09:11:21
Size: 7998
Comment:
Revision 305 as of 2018-02-19 14:42:39
Size: 8621
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/1/23 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
2017/2/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180220.png||width=1200}}
Line 18: Line 18:

 * Pump down
  * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 57: Line 54:
2017/1/26(Fri.) 2017/2/19(Mon.)
Line 59: Line 56:
 * Remote participants by eZuce:  * Remote participants by eZuce: None
  * Recovery from the power outage in the morning.
Line 62: Line 60:
  * Alignment and ETMY: *Izumi, Enomomoto
   * Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
Glitch is still there but even if measurement with no glitch time has still no coherence.
Line 63: Line 64:
  * Vacuum
   * ターボポンプを入れた。

  * Alignment
   * Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。
   
  * AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada
   * k1iy0への電源ケーブルの仕上げ。
   * IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。
 * PR RT models will be modified for Watch dog bug or something.
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
Line 74: Line 68:
  * 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。
  * Alignment: Oplevのセンタリング。
  * ETMY: Enomomoto, Izumi
   * Damping tuning
Line 77: Line 71:

* Laser hazard: Upstream of IMMT line
 * Laser hazard: Upstream SR2-3 line.
Line 81: Line 74:
  * Week of 1/22
   * 1/24: Pump down.
   * 1/25: Turbo pump on.
  * Week of 2/19
   * 2/19 Recovering for power down.
   * ETMY tuninng.
Line 85: Line 78:
  * Week of 1/29
   * 1/29,30 leak check.
   * 1/30 Opening ETMY gate valve.
  * Week of 2/26
   * Beam alignment to REFL port.
Line 89: Line 81:
  * Week of 2/5
   * 2/5 Cooling start.
  * week of 3/5
   * IYC door will be closed.
Line 92: Line 84:
  * week of 3/12
   * Connecting ducts at corner.
Line 94: Line 88:
  * Network cableの整理
  * ピコモーターの反応がなくなる。
  * ETMY TF shows Q is getting lower and the resonant frequency is getting higher. Something is touching somewhere?
Line 107: Line 100:
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/19 updated KAGRA/Commissioning/Commissioning_schedule_20180220.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/19(Mon.)

  • Remote participants by eZuce: None
    • Recovery from the power outage in the morning.
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto
      • Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.

Glitch is still there but even if measurement with no glitch time has still no coherence.

  • PR RT models will be modified for Watch dog bug or something.
  • Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Izumi
      • Damping tuning
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Connecting ducts at corner.
  • Issues
    • ETMY TF shows Q is getting lower and the resonant frequency is getting higher. Something is touching somewhere?

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)