Line 11: | Line 11: |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/2/12 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180213.png||width=1200}} |
Line 54: | Line 54: |
2017/1/29(Mon.) | 2017/2/14(Wed.) |
Line 57: | Line 57: |
* Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work! | |
Line 59: | Line 60: |
* ETMY: *Enomomoto * Calibration at cryopayload was performed. * Cryo: mirror temperature: 220K. * Green reached ETMY * PR2 had 500urad misalignment. |
|
Line 60: | Line 66: |
* Alignment * Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百mrad)でドリフトがあるもようだが、範囲は狭まって来ている。 |
|
Line 64: | Line 69: |
* Vacuum: leak check * Alignment: Oplevのセンタリング。 |
* ETMY: Enomomoto, Izumi * Returning IR light will be checked around BS. * Leveler wil be removed in the more * Green reached ETMY * PR2 had 500urad misalignment. |
Line 68: | Line 77: |
* Laser hazard: Upstream of IMMT line | * Laser hazard: IMM in the morning, SR2-3 in the afternoon. |
Line 71: | Line 80: |
* Week of 2/13 * Waiting for cooling the mirror. * ETMY tuninng. |
|
Line 72: | Line 84: |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. |
* Week of 2/19 * ETMY tuninng. |
Line 76: | Line 87: |
* Week of 2/5 * 2/5 Cooling start. |
* Week of 2/26 * Beam alignment to REFL port. * Issues * AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed. * DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know. |
Line 80: | Line 95: |
* Issues * Network cableの整理 * ピコモーターの反応がなくなる。 |
|
Line 94: | Line 106: |
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/12 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/14(Wed.)
- Remote participants by eZuce: None
- Enonomoto-kun started joining to commissioning. No one has to hesitate to join commissioning work!
- Report of work (*:responsible person)
- ETMY: *Enomomoto
- Calibration at cryopayload was performed.
- Cryo: mirror temperature: 220K.
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: *Enomomoto
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Returning IR light will be checked around BS.
- Leveler wil be removed in the more
- Green reached ETMY
- PR2 had 500urad misalignment.
- ETMY: Enomomoto, Izumi
- Laser hazard: IMM in the morning, SR2-3 in the afternoon.
- Weekly
- Week of 2/13
- Waiting for cooling the mirror.
- ETMY tuninng.
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- Week of 2/13
- Issues
- AOS: Temperature inside clean booth is higher than outside area. One of the view port mirror brought from ITMY area into clean booth was dewed.
- DGS: k1boot was cleaned up. No filter can be updated yesterday because of a missing file. If there is something wrong, please let DGS group know.
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)